SE423 · Software Project Management · Chapter 1 (Parts 1, 1.2, 1.3)

Before you manage a project,
meet the field that runs on it.

All of Chapter 1 on one page: Part 1 introduces the field, PMBOK and the 12 principles, Part 1.2 walks the 8 performance domains, and Part 1.3 covers tailoring and the models, methods and artifacts you tailor with. Ideas that appear in more than one part are written out once, with "Also in" links to the other places they show up.

SYSTEM FOR VALUE DELIVERY Senior Leadership Portfolios Programs & Projects Operations OUTCOME Benefits → Value Component → Outcome → Benefits → Value — the chain every PM decision serves
PART 1 · 70 SLIDES

Introduction

What project management is, where it came from, who does it, PMBOK, the System for Value Delivery and the 12 principles.

Part 1 § 1·01 — DEFINITION & WHY IT MATTERS

What is Project Management?

Memory hook
"Guiding the work to the outcome, not just doing the work."
Project management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements — and it means guiding the project work to deliver the intended outcomes, using any mix of approaches (predictive, hybrid, adaptive).

Two official framings, same idea

definition

1. The application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
2. Project management refers to guiding the project work to deliver the intended outcomes. Project teams can achieve the outcomes using a broad range of approaches (e.g., predictive, hybrid, and adaptive).

Why the field is exploding right now
87.7M

People PMI projects employers will need in project-management-oriented roles by 2027.

2.3M

New PM employees needed each year to meet global talent demand by 2030 (PMI 2021 Talent Gap report).

$97M

Wasted per every $1 billion spent on projects, per PMI's Pulse of the Profession® report.

$135.2B

Projected size of Saudi Arabia's AI market by 2030 under the Smart Government Strategy — ~12.4% of GDP.

$24.7B

Saudi Arabia's 2025 government tech spending (SR93B) — the highest in the world, 21.7% of national spending.

3

Top skills employers want in new grads — team-work, problem-solving, verbal communication — all core PM skills.

Also in Part 1.2 · Development Approach domain · Part 1.3 · choosing the initial approach

Part 1 § 1·02 — HISTORY

From the pyramids to the PMO

A profession growing "at a very rapid pace" — understanding where it came from explains why PMI, certification, and PMOs exist today.

Ancient — Debated origins

The pyramids and the Great Wall

Some argue that building the Egyptian pyramids was a project, as was building the Great Wall of China — massive, coordinated, goal-directed endeavors, even without the word "project management" yet.

Focus: the argument that "projects" long predate the formal discipline.
1946 — The Manhattan Project

Most-cited origin of "modern" project management

Led by Dr. Oppenheimer: a three-year, $2 billion (1946 dollars) project. It had a separate project manager and technical manager — an early split between managing the project and managing the technical work, which is still a live distinction today.

Key fact for exams: 3 years · $2B (1946$) · two distinct manager roles.
1990s — Rise of the PMO

Companies start creating Project Management Offices

As the number and complexity of projects grew, organizations began forming Project Management Offices (PMOs) — organizational units responsible for coordinating the project management function across the organization.

PMO adoption by firm size: Small (<$100M revenue) 75% · Mid-size ($100M–$1B) 83% · Large (>$1B) 95%.
Today — Global dynamics reshaping practice

Talent, agility, and benefits realization

Several global dynamics are forcing organizations to rethink their practices: talent development for project/program managers is a top concern, basic PM techniques are now core competencies, organizations want more agile approaches, and benefits realization is a key success metric.

This is the world PMI's certification growth reflects (see next section).
Project Management Certification

The Project Management Institute (PMI) is the leading organization advancing the PM profession. PMI provides certification as a Project Management Professional (PMP®), and the number of people earning PMP® certification is increasing quickly (active holders roughly doubled from ~510K in 2012 to a peak above 1.25M around 2021–2022).

For students: you can join PMI at a reduced fee and earn the Certified Associate in Project Management (CAPM) certification — the entry-level counterpart to the PMP.
Ethics in Project Management

Ethics, loosely defined, is a set of principles that guide decision making based on personal values of "right" and "wrong." Project managers often face ethical dilemmas. To earn PMP® certification, applicants must agree to PMI's Code of Ethics and Professional Conduct — and several PMP® exam questions relate to professional responsibility, including ethics.

The PMI Code of Ethics rests on four values: Responsibility, Respect, Fairness, and Honesty.
PDF page 10Percentage of firms with a PMO, by company size.
Part 1 § 1·03 — THE PROJECT MANAGER

The role, the responsibilities, the competencies

What PMs are on the hook for

responsibilities

Project managers are mainly responsible for all issues related to the software project; issues vary by scale, but the common ones are: Schedule, Budget, Quality, Delivery of products, and Locking in resources. In practice, most of a PM's time is consumed chasing and collecting the status of project tasks.

The role

Job descriptions vary, but most include planning, scheduling, coordinating, and working with people to achieve project goals. 97% of successful projects were led by experienced project managers, who can often help influence success factors.

Skills PMs need

Be comfortable with change · Understand the organizations they work in and with · Be able to lead teams to accomplish project goals.

14 competencies to memorize

People skills · Leadership · Listening · Integrity/ethical behavior/consistency · Building trust · Verbal communication · Building teams · Conflict resolution/management · Critical thinking/problem solving · Balancing priorities · Negotiating · Influencing the organization · Mentoring · Process and technical expertise.

Chunking aid — 14 competencies, 3 buckets
People-facing · Thinking · Doing-the-craft
People-facing (7): people skills, leadership, listening, integrity, trust, communication, team-building.
Thinking/managing (5): conflict resolution, critical thinking, balancing priorities, negotiating, influencing the organization.
Craft (2): mentoring, process & technical expertise.
Advantages of using formal project management

Better resource control

Financial, physical, and human resources.

Improved customer relations

Structured engagement with stakeholders.

Shorter dev times

Lower costs, improved productivity.

✓

Higher quality

Increased reliability, higher profit margins.

Better internal coordination

Positive impact on meeting strategic goals.

Higher worker morale

Less stress, fewer overworked personnel.

PDF page 57Where project management principles overlap general management principles.
Part 1 § 1·04 — PMBOK

Project Management Body of Knowledge

The reference standard the rest of this course — and this chapter's vocabulary — is built on.

Purpose of The Standard for Project Management

PMBOK v7

The Standard for Project Management provides a basis for understanding project management and how it enables intended outcomes. It applies regardless of industry, location, size, or delivery approach (predictive, hybrid, or adaptive). It describes the system within which projects operate — including governance, possible functions, the project environment, and the relationship between project management and product management.

8 Project Performance Domains (PMBOK v7)

Stakeholders · Team · Development Approach & Life Cycle · Planning · Project Work · Delivery · Measurement · Uncertainty.

The domains are written out once, in full, in Part 1.2 (definitions, memory hook, outcome checks), so they are not repeated here.

Don't confuse these with the 12 Principles (§08). Domains are the areas of work you manage day to day; principles are the underlying guidelines that shape how you manage them. "Risk" is a principle, not a domain — the closest domain is "Uncertainty."
PDF page 22The eight project performance domains.
Part 1 § 1·05 — KEY TERMS AND CONCEPTS

The vocabulary PMBOK builds everything else on

Outcome

An end result or consequence of a process or project. Broader than outputs/artifacts — focuses on the benefits and value the project was undertaken to deliver.

Portfolio

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. Example: a company's R&D programs, marketing campaigns, or infrastructure upgrades.

Program

Related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually. Example: a company-wide digital transformation initiative.

Project

A temporary endeavor undertaken to create a unique product, service, or result. "Temporary" means a beginning and an end to the work or a phase of it. Projects can stand alone or be part of a program or portfolio.

Product

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item.

Project Manager

The person assigned by the performing organization to lead the project team, responsible for achieving the project objectives — facilitating team work and managing processes to deliver intended outcomes.

Project Team

A set of individuals performing the work of the project to achieve its objectives.

Project Management Team

The members of the project team who are directly involved in project management activities (a subset of the full project team).

System for Value Delivery

A collection of strategic business activities aimed at building, sustaining, and/or advancing an organization. Portfolios, programs, projects, products, and operations can all be part of it.

Value

The worth, importance, or usefulness of something. Different stakeholders perceive it differently: customers via features/functions, organizations via business value (benefits minus cost), and society via community or environmental contribution.

Part 1 § 1·06 — A SYSTEM FOR VALUE DELIVERY

How projects actually turn into value

Provides a context for value delivery, governance, project functions, the project environment, and product management.

The chain to memorize
Component → Outcome → Benefits → Value
The components in a value delivery system (portfolios, programs, projects, products, operations) create deliverables used to produce outcomes. Outcomes create benefits (gains realized by the organization). Benefits, in turn, create value (something of worth, importance, or usefulness).
Component
→
Deliverable
→
Outcome
→
Benefit
→
Value
Ways projects produce value
🆕

Creating a new product, service, or result that meets customer/end-user needs.

Creating positive social or environmental contributions.

Improving efficiency, productivity, effectiveness, or responsiveness.

Enabling changes needed for organizational transition to a desired future state.

Sustaining benefits enabled by previous programs, projects, or operations.

Value Delivery Components

nested structure

Portfolios, programs, projects, products, and operations can be used individually and collectively to create value. Working together, they compose a system for delivering value aligned with the organization's strategy. Any project or program could include products, and operations can directly support/influence portfolios, programs, and projects (as well as functions like payroll, supply chain, finance, HR, customer service).

This system for value delivery sits inside the organization's internal environment (policies, procedures, methodologies, governance structures), which itself sits inside the external environment (economy, competitive landscape, legislative constraints).

Information Flow

feedback loop

A value delivery system works best when information and feedback are shared consistently among all components, keeping the system aligned with strategy and in harmony with the environment.

Flowing down

Senior Leadership shares strategy with Portfolios → Portfolios share desired outcomes, benefits, and value with Programs & Projects → Programs & Projects pass deliverables + support/maintenance info to Operations.

Flowing back up

Operations feed back updates, fixes, and adjustments to Programs & Projects → Programs & Projects report performance information and progress to Portfolios → Portfolios report portfolio performance to Senior Leadership. Outcomes/benefits/value performance analysis flows the whole loop back to Senior Leadership.

Organizational Governance Systems

Works alongside the value delivery system to enable smooth workflows, manage issues, and support decision making. A governance framework can include oversight, control, value assessment, integration among components, and decision-making capabilities — plus an integrated structure for evaluating changes, issues, and risks. Project governance is aligned with program and/or organizational governance, and includes defining the authority to approve changes.

Functions Associated with Projects

People drive project delivery by executing functions — fulfilled by one person, a group, or combined into defined roles. Coordination can be decentralized (teams self-organize/self-manage) or centralized (a designated project manager leads) — and centralized projects can still include self-organized sub-teams for portions of the work.

# Function Example
1 Provide oversight and coordination Monitoring progress and performance
2 Present objectives and feedback Defining success criteria and desired outcomes
3 Facilitate and support Hosting meetings, workshops, stand-ups
4 Perform work and contribute insights Completing assigned deliverables
5 Apply expertise Advising on technical/domain-specific matters
6 Provide business direction and insight Identifying market trends or customer needs
7 Provide resources and direction Allocating budget, personnel, infrastructure
8 Maintain governance Enforcing regulatory and internal standards
The Project Environment — Internal

Factors internal to the organization, arising from the org itself, a portfolio, a program, another project, or a combination. Includes artifacts, practices, and internal knowledge — e.g. process assets, governance documentation, data assets, knowledge assets, infrastructure, information technology software.

The Project Environment — External

Factors external to the organization can enhance, constrain, or have a neutral influence on project outcomes — e.g. marketplace conditions, social/cultural influences, regulatory environment, commercial databases, academic research, industry standards, financial considerations, physical environment.

Also in Part 1.3 · organization and environment factors

PDF page 32The components of a value delivery system.
PDF page 33How the value delivery components fit together.
PDF page 36Information flow between operations, programs and projects.
PDF page 37Organizational governance systems around the project.
Part 1 § 1·07 — PRODUCT MANAGEMENT CONSIDERATIONS

Where projects meet the product's life cycle

Portfolio, program, and product management are beyond the scope of the PMI standard and this course — but understanding each discipline and the relationships between them provides useful context for projects whose deliverables are products. Product management involves integrating people, data, processes, and business systems to create, maintain, and develop a product or service throughout its product life cycle.

The product life cycle
Introduction
Growth
Maturity
Decline / Retirement

A series of phases representing a product's evolution — from introduction, through growth and maturity, to retirement. Product management may initiate programs or projects at any point in the life cycle to create or enhance specific components, functions, or capabilities. The initial product may begin as a project's deliverable, and later programs/projects can add value throughout the cycle (e.g. Project 1: initial creation → Projects 2–3: more features/additions → Projects 4–6: revisions → Project 7: retirement — all under Portfolio Governance).

Decision tree — which form of product management applies?
Scope of the work decides the structure.
Match the situation to the right approach below.
IF the product is very large/long-running and one or more life-cycle phases are complex enough to need a coordinated set of related projects...
→ Program management within a product life cycle (e.g. modernizing a product after years of launch).
IF the work is ongoing enhancement/improvement of product capabilities, chartered project-by-project as needed...
→ Project management within a product life cycle (e.g. modernizing the UI after years of launch — portfolio governance charters individual projects).
IF the full product life cycle is bounded within the purview of one program...
→ Product management within a program (e.g. building a proof-of-concept to showcase potential directions of a given program).
PDF page 49A product life cycle, from introduction to retirement.
Part 1 § 1·08 — PROJECT MANAGEMENT PRINCIPLES

The 12 principles of PMBOK v7

Principles are foundational guidelines for strategy, decision making, and problem solving — but unlike laws or rules, PM principles are not prescriptive. They guide behavior; they don't dictate a single "correct" method. They're internally consistent (no principle contradicts another), though practical dilemmas can still arise, and they can overlap with general management principles.

Memory hook — all 12, in order
"Stewards Trust Stakeholders' Value; Systems Leaders Tailor Quality, Complexity, Risk, Adapt & Change."
Stewardship · Team · Stakeholders · Value · Systems Thinking · Leadership · Tailoring · Quality · Complexity · Risk · Adaptability & Resiliency · Change
Stewardship1/12

Be a diligent, respectful, and caring steward.

  • Act responsibly and ethically, with integrity, care, trustworthiness, and compliance.
  • Spans responsibilities inside and outside the organization.
  • Holistic view: financial, social, technical, and sustainable environmental awareness.
Team2/12

Create a collaborative project team environment.

  • Projects are delivered by project teams.
  • Teams work within organizational/professional cultures, often forming their own "local" culture.
  • Collaboration aligns cultures, enables learning/development, and optimizes contribution.

Also in Part 1.2 · Team domain

Stakeholders3/12

Effectively engage with stakeholders.

  • Stakeholders influence projects, performance, and outcomes.
  • Project teams serve stakeholders by engaging with them.
  • Proactive engagement advances value delivery.

Also in Part 1.2 · Stakeholder domain

Value4/12

Focus on value.

  • Value is the ultimate indicator of project success.
  • Can be realized during, at the end of, or after the project.
  • Defined quantitatively and/or qualitatively; teams adapt to maximize expected value.

Also in Part 1 · System for Value Delivery · Part 1.2 · Delivery domain

Systems Thinking5/12

Recognize, evaluate, and respond to system interactions.

  • A project is a system of interdependent, interacting domains of activity.
  • Take a holistic view of how project parts interact with each other and external systems.
  • Systems constantly change — stay responsive.
Leadership6/12

Demonstrate leadership behaviors.

  • Any project team member can demonstrate leadership behaviors.
  • Leadership ≠ authority.
  • Effective leaders adapt style to the situation and to individual motivation, and model honesty, integrity, and ethics.

Also in Part 1.2 · Team domain (management vs leadership)

Tailoring7/12

Tailor based on context.

  • Each project is unique.
  • Design the development approach using "just enough" process for the desired outcome, maximizing value, managing cost, and enhancing speed.
  • Tailoring is iterative — continuous throughout the project.

Also in Part 1.3 · Tailoring

Quality8/12

Build quality into processes and deliverables.

  • Satisfies stakeholder expectations and fulfills project/product requirements.
  • Focuses on meeting acceptance criteria for deliverables.
  • Ensures processes are appropriate and as effective as possible.

Also in Part 1.2 · Delivery domain (quality, COQ)

Complexity9/12

Navigate complexity.

  • Complexity results from human behavior, system interactions, uncertainty, and ambiguity.
  • Can emerge at any point in the project, introduced by scope, communications, stakeholders, risk, or technological innovation.
  • Teams stay vigilant and use methods to reduce complexity's amount/impact.

Also in Part 1.2 · Uncertainty domain (complexity)

Risk10/12

Optimize risk responses.

  • Risks can be positive (opportunities) or negative (threats), addressed continually.
  • An organization's risk attitude, appetite, and threshold shape the response.
  • Responses should be appropriate, cost-effective, realistic, agreed by stakeholders, and owned by someone.

Also in Part 1.2 · Uncertainty domain (threats, opportunities)

Adaptability & Resiliency11/12

Embrace adaptability and resiliency.

  • Adaptability = ability to respond to changing conditions.
  • Resiliency = ability to absorb impacts and recover quickly from a setback or failure.
  • Focusing on outcomes rather than outputs facilitates adaptability.

Also in Part 1.2 · Team domain (high-performing teams)

Change12/12

Enable change to achieve the envisioned future state.

  • A structured approach helps the transition from current to future state.
  • Change can originate internally or externally; not everyone embraces it.
  • Too much change too fast → change fatigue/resistance. Stakeholder engagement and motivation assist adoption.
Where principles come from: Principles for a profession serve as foundational guidelines for strategy, decision making, and problem solving. Some professions treat principles as prescriptive laws/rules — PM principles are not; they guide behavior broadly, and principles can, but do not necessarily, reflect morals (that's what a code of ethics is for). PM principles also overlap with general management principles — both focus on delivering value, for example.
PDF page 21The twelve principles of PMBOK v7.
PDF page 59Principle: be a diligent, respectful and caring steward.
PDF page 60Principle: create a collaborative project team environment.
PDF page 61Principle: effectively engage with stakeholders.
PDF page 62Principle: focus on value.
PDF page 63Principle: recognize, evaluate and respond to system interactions.
PDF page 64Principle: demonstrate leadership behaviors.
PDF page 65Principle: tailor based on context.
PDF page 66Principle: build quality into processes and deliverables.
PDF page 67Principle: navigate complexity.
PDF page 68Principle: optimize risk responses.
PDF page 69Principle: embrace adaptability and resiliency.
PDF page 70Principle: enable change to achieve the envisioned future state.
PART 1.2 · 107 SLIDES

Project Performance Domains

The 8 domains as one system, each with definitions and an outcome → check table.

Part 1.2 § 1.2·01 — WHAT A PERFORMANCE DOMAIN IS

One system, eight interdependent areas of focus

Definitions, straight from the slides, before anything else.

Memory hook
"Steady Teams Design Plans, Push Delivery, Measure Uncertainty."
Stakeholders → Team → Development Approach & Life Cycle → Planning → Project Work → Delivery → Measurement → Uncertainty. Read the sentence in order and the eight domains fall out of it.
Project performance domain
A group of related activities that are critical for the effective delivery of project outcomes.
How they behave
Interactive, interrelated, and interdependent — they work in unison to achieve desired project outcomes.
Timing
Performance domains run concurrently throughout the project, regardless of how value is delivered (frequently, periodically, or at the end).
What drives them
The Principles of Project Management (be a diligent steward, engage stakeholders, focus on value, tailor based on context, embrace adaptability, etc.) guide the behaviors performed inside every domain.
Why this chapter matters even though most of these domains get their own dedicated chapter elsewhere in the course (Stakeholders, Team, Development Approach & Life Cycle are all covered in depth separately) — this chapter is the framework overview: it's the only place that shows how all eight fit together as one system, each with a formal definition and a predictable Outcome → Check pattern you'll see repeated for every single domain.
§ 01B — THE EIGHT, AT A GLANCE

Click through the wheel

01

Stakeholders

Productive relationships with everyone who can affect or be affected by the project.

02

Team

The people producing the deliverables — management vs. leadership, culture, high performance.

03

Development Approach & Life Cycle

Predictive, hybrid, or adaptive — and the phases that connect start to finish.

04

Planning

Estimates, schedules, budgets, resources, procurement — organizing the coordinated path.

05

Project Work

Establishing processes, managing physical resources, and fostering learning.

06

Delivery

Scope and quality that actually realize the business value the project was chartered to deliver.

07

Measurement

Metrics, baselines, dashboards — turning data into timely, appropriate action.

08

Uncertainty

Risk, ambiguity, complexity, and volatility — and how to work with each of them.

Also in Part 1 · the 12 principles that drive every domain

PDF page 2The eight performance domains as one interacting system.
Part 1.2 § 1.2·02 — DOMAIN 1

Stakeholder Performance Domain

"Technical project management skills are important, but having the interpersonal and leadership skills to work effectively with stakeholders is maybe more important." — straight off the slide.

Stakeholders

relationships & alignment

Addresses activities and functions associated with stakeholders. A stakeholder is an individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio. Stakeholder analysis systematically gathers and analyzes quantitative and qualitative information to determine whose interests should be taken into account throughout the project — including internal and external stakeholders, and those supportive, unsupportive, or neutral.

The three-ring stakeholder map

Outer ring: Suppliers, Customers, End Users, Regulatory Bodies. Middle ring: Governing Bodies, PMOs, Steering Committees. Inner ring (closest to the work): Project Manager, Project Management Team, Project Team.

Desired outcomes
  • A productive working relationship with stakeholders throughout the project.
  • Stakeholder agreement with project objectives.
  • Beneficiaries are supportive/satisfied; opponents don't negatively impact outcomes.
Outcome → Check table
Productive working relationship Observed relationships; movement of stakeholders along a continuum of engagement indicates relative satisfaction.
Stakeholder agreement with objectives A significant number of scope/requirement changes may indicate stakeholders are not engaged or aligned.
Beneficiaries supportive; opponents contained Stakeholder behavior; surveys, interviews, focus groups; a review of the issue & risk registers.
PDF page 3The stakeholder performance domain.
PDF page 4Stakeholder analysis: who they are and how they are affected.
Part 1.2 § 1.2·03 — DOMAIN 2

Team Performance Domain

Addresses activities and functions associated with the people responsible for producing project deliverables that realize business outcomes.

Memory hook
"Management is the means. Leadership is about the people."
Management activities: effective processes, planning, coordinating, measuring, monitoring. Leadership activities: influencing, motivating, listening, enabling. Both matter — but leadership should be practiced by everyone, while management may be centralized or distributed.

Centralized vs. Distributed Management

who's accountable?
Decentralized Centralized
Middle/low-level managers have decision-making power A few upper-management members have decision-making power
Authority given to those closer to stakeholders Authority given to those at the top of the chain of command
Organizations are self-sufficient More standardization
Faster decision making More control
More expensive Less expensive
More creativity Limited creativity
Centralized: accountability is assigned to one individual (e.g. the project manager); a project charter authorizes them to form the team. Distributed: the team self-organizes; a facilitator (not a designated PM) enables communication and collaboration, and this role may shift among members.
Common aspects of team development
  • Vision & objectives
  • Roles & responsibilities
  • Project team operations
  • Guidance (team-wide or task-specific)
  • Growth (identify strengths/gaps, set improvement goals collaboratively)
Behaviors that build team culture

Transparency, integrity, respect, positive discourse, support, courage, celebrating success — modeled by the PM to keep the environment safe, respectful, nonjudgmental.

Components of Emotional Intelligence
Self-Awareness
How do you affect the team? How does the team affect you?
Self-Management
Think before you act. Build trust.
Social Awareness
Be empathetic. Employ active listening.
Social Skill
Establish rapport, build effective teams, manage attitude.
High-performing team factors: open communication, shared understanding, shared ownership, trust, collaboration, adaptability, resilience, empowerment, recognition.

Leadership skills: establishing & maintaining vision, critical thinking, motivation, interpersonal skills.

Tailoring leadership style (autocratic, democratic, laissez-faire, transactional, servant, etc.) depends on: experience with the project type, maturity of team members, organizational governance structures, and whether the team is distributed.

Also in Part 1 · principles 2, 6 and 11

PDF page 6The team performance domain.
PDF page 10Decentralized against centralized team management.
PDF page 15The leadership skills a project team needs.
PDF page 16The components of emotional intelligence.
Part 1.2 § 1.2·04 — DOMAIN 3

Development Approach & Life Cycle Performance Domain

Addresses activities and functions associated with the development approach, cadence, and life cycle phases of the project.

Deliverable
Any unique, verifiable product, result, or capability to perform a service, required to complete a process, phase, or project.
Development approach
The method used to create and evolve the product/service/result — predictive, iterative, incremental, adaptive, or hybrid.
Cadence
A rhythm of activities conducted throughout the project.
Project phase
A collection of logically related activities culminating in one or more deliverables.
Project life cycle
The series of phases a project passes through from start to completion.
Memory hook
"Deliverable decides development, development decides cadence, cadence decides life cycle."
The type of deliverable determines how it can be developed → the development approach influences delivery cadence → cadence + approach determine the project life cycle and its phases. It's a one-way chain, in that order.
Predictive

Waterfall

Requirements defined, collected, analyzed upfront. Used with significant investment/high risk needing frequent reviews & change control. Scope, schedule, cost, resources, risk are well-defined early and relatively stable. Reduces uncertainty early; heavy upfront planning.

Hybrid

Mix of both

Combines predictive + adaptive elements. Useful when requirements carry uncertainty/risk, or when deliverables can be modularized / built by different teams.

Adaptive

Agile

For requirements with high uncertainty/volatility that will change throughout the project. Clear vision set upfront; requirements refined via feedback. Iterative + incremental; iterations often 1–2 weeks with a demo at the end. Team is heavily engaged in planning each iteration.

Note the nuance: agility is a broader mindset than any one framework — but agile approaches specifically can be considered adaptive.
Considerations for selecting an approach

Product variables: degree of innovation, requirements certainty, scope stability, ease of change, delivery options, risk, safety requirements, regulations.

Project variables: stakeholders (adaptive needs heavy involvement; product owner prioritizes work), schedule constraints (early delivery favors iterative/adaptive), funding availability (funding uncertainty favors adaptive; an MVP needs less investment and enables market testing).

Organizational variables: structure, culture, capability, team size & location.

Delivery cadence

The timing/frequency of deliveries — single, multiple, or periodic. For digital products, continuous delivery ships feature increments immediately via small batches + automation (seen in DevOps, #noprojects, Continuous Digital).

Phase gate / stage gate review: checks that a phase's desired outcomes or exit criteria were achieved before moving to the next phase. Exit criteria may tie to deliverable acceptance criteria, contractual obligations, or performance targets.

Sample predictive life cycle: Feasibility → Design → Build → Test → Deploy → Close. Sample incremental approach: Concept → repeating Plan/Design/Build cycles → Close.

Also in Part 1.3 · step 1 of tailoring selects this approach

PDF page 19The development approach and life cycle performance domain.
PDF page 23The spectrum of development approaches, predictive through adaptive.
PDF page 32Life cycle and phase definitions.
PDF page 33A community centre project life cycle.
Part 1.2 § 1.2·05 — DOMAIN 4

Planning Performance Domain

Addresses activities and functions associated with the initial, ongoing, and evolving organization and coordination necessary for delivering project deliverables and outcomes.

Memory hook — the one that trips everyone up
"Accuracy is a bullseye. Precision is a tight cluster — anywhere."
Accuracy = correctness: how well your plan predicts reality (estimate $100K, actual $102K → accurate). Precision = exactness: the level of detail and consistency in your assumptions. An estimate can be precise (built from a detailed cost breakdown) yet not accurate (the project still ends up costing far more or less).
Estimate
A quantitative assessment of the likely amount or outcome of a variable — cost, resources, effort, or duration.
Accuracy
Correctness — how well the plan predicts reality.
Precision
Exactness — the level of detail and consistency in planning assumptions.
Planning overview: purpose is to proactively develop an approach to create the deliverables. High-level planning may begin before project authorization. The team progressively elaborates a vision statement, project charter, business case, or similar. It's increasingly common for planning to weigh social/environmental impacts alongside financial ones (e.g. a product life cycle assessment).

Planning begins with understanding the business case, stakeholder requirements, and the project/product scope. Product scope = features and functions of the product/service/result. Project scope = the work performed to deliver that product with those features/functions.
Decomposing scope

Predictive: start with high-level deliverables, decompose via a scope statement and/or WBS.
Iterative/Incremental: themes/epics → features → user stories/backlog items. Novel or risky work is prioritized to reduce uncertainty before major investment (the last responsible moment: defer a decision until the cost of further delay would exceed the benefit).

Schedules — predictive (5 steps)
  1. Decompose scope into activities
  2. Sequence related activities
  3. Estimate effort/duration/people/resources
  4. Allocate people & resources by availability
  5. Adjust until an agreed-upon schedule is reached
Four types of dependencies
Mandatory Contractually required or inherent in the work. Usually cannot be modified.
Discretionary Based on best practices or preferences. May be modifiable.
External Between project and non-project activities. Usually cannot be modified.
Internal Between one or more project activities. May be modifiable.
Adaptive scheduling

A high-level release plan sets features per release; each release has 2+ iterations; each iteration adds value (features, risk reduction, experimentation). Future-release planning stays high-level so it can still change based on feedback. Often uses timeboxes: team estimates what it can do, self-manages, demonstrates completed work, then reprioritizes the backlog.

BUDGET, RESOURCES & PROCUREMENT
Budget build-up

Work Cost Estimates aggregate into the Cost Baseline (time-phased budget, allocated across the schedule) → add Contingency Reserve → add Management Reserve → Project Budget.

Contingency reserve: for identified risks, controlled by the PM.
Management reserve: for unexpected, in-scope work (unknown risks); may be managed by the sponsor, product owner, or PMO.
Physical resources & procurement

Physical resources = anything that isn't a person (materials, equipment, software, licenses...). Planning includes supply chain, logistics, lead time for delivery/movement/storage. A make-or-buy analysis identifies what's built in-house vs. purchased externally once high-level scope is known — this impacts both team and schedule.

Outcome → Check table (Planning)
Progresses organized, coordinated, deliberate Performance review vs. baselines shows the project is on plan; variances within thresholds.
Holistic approach to delivering outcomes Delivery schedule, funding, resource availability, procurements show no gaps or misalignment.
Evolving information is elaborated Initial vs. current information about deliverables/requirements shows appropriate elaboration.
Time spent planning is appropriate Plans/documents show a level of planning appropriate for the project.
Planning info sufficient for expectations Communications plan and stakeholder info show communications are sufficient.
Process exists for adapting plans Backlogs show adaptation; change logs/change control board minutes show the process is applied.
PDF page 35The planning performance domain.
PDF page 44A release and iteration plan.
PDF page 48How a budget is built up from estimates.
Part 1.2 § 1.2·06 — DOMAIN 5

Project Work Performance Domain

Addresses activities and functions associated with establishing project processes, managing physical resources, and fostering a learning environment.

Project work keeps the team focused and activities running smoothly. It includes but isn't limited to: managing the flow of existing work, new work, and changes; keeping the team focused; establishing efficient systems/processes; communicating with stakeholders; managing material/equipment/supplies/logistics; working with contracting professionals on procurements and contracts; monitoring changes that can affect the project; and enabling project learning and knowledge transfer.
Project processes

The PM and team establish and periodically review the processes used to conduct the work — e.g. reviewing task boards for bottlenecks, work-flow rate, or impediments. Process tailoring optimizes process for the project's needs: large/critical projects generally carry more process than small/less-significant ones. Ways to optimize: lean production methods, retrospectives / lessons learned, asking "where is the next best funding spent?" Teams spend just enough time on process-conformance review to maximize benefit while still satisfying governance needs — time spent tracking conformance is time not spent delivering outcomes.

Balancing competing constraints

Constraints — fixed delivery dates, regulatory compliance, a predetermined budget, quality policies — can shift throughout the project. A new stakeholder requirement may mean expanding schedule and budget; a budget cut may mean relaxing a quality requirement or reducing scope. This ongoing balancing act may involve presenting alternatives to the customer/sponsor/product owner, or may be entirely within the team's own authority to trade off.

Working with Procurement

bid documents

Project managers usually don't have contracting authority — they work with contracting officers/professionals who know contracts, laws, and regulations. Organizations have rigorous policies identifying who has authority, its limits, and the process to follow. Before going out to bid, the PM and technically qualified team members work with contracting professionals to develop the RFP, statement of work (SOW), and terms and conditions.

Term Meaning / example
Bid Documents All documents used to solicit information, quotations, or proposals from prospective sellers.
Bidder Conference Pre-bid meetings ensuring vendors share a common understanding. Also: contractor/vendor/pre-bid conferences.
Request for Information (RFI) Learning what capabilities/vendors exist before deciding on a solution (e.g. exploring software platforms).
Request for Proposal (RFP) Inviting vendors to bid on building a specific, already-decided solution.
Request for Quote (RFQ) Asking multiple vendors for best price/timeline on a well-defined need (e.g. 500 laptops to spec).
Learning through the project
Explicit knowledge
Knowledge codified using symbols — words, numbers, pictures.
Tacit knowledge
Personal knowledge that's hard to articulate/share — beliefs, experience, insights.
Desired outcomes
  • Efficient and effective project performance
  • Processes appropriate for project and environment
  • Appropriate communication with stakeholders
  • Efficient management of physical resources
  • Effective management of procurements
  • Improved team capability from continuous learning
PDF page 53The project work performance domain.
Part 1.2 § 1.2·07 — DOMAIN 6

Delivery Performance Domain

Addresses activities and functions associated with delivering the scope and quality that the project was undertaken to achieve.

Definition of Done (DoD)
A checklist of all criteria required for a deliverable to be considered ready for customer use.
Quality
The degree to which a set of inherent characteristics fulfills requirements.
Cost of Quality (COQ)
All costs incurred over the product's life from investing in preventing nonconformance, appraising conformance, and failing to meet requirements.
Memory hook
"Scope says WHAT. Quality says HOW WELL."
Scope and requirements focus on what needs to be delivered. Quality focuses on the performance levels required to be met — often reflected in completion criteria, the Definition of Done, the SOW, or requirements documentation.
Delivery of value

Development approaches that release deliverables throughout the life cycle can start delivering value to the business early — and business value often keeps accruing long after the project itself has ended. A business case document provides the justification and a projection of anticipated value; its format varies with the chosen development approach and life cycle.

Cost of quality — who pays

Much of the cost tied to quality is borne by the sponsoring organization — reflected in policies, procedures, and work processes — even though it's employed by the project (overhead, training, process audit). The COQ methodology is used to find the right balance between investing in prevention and appraisal, versus risking defect/product failure.

Suboptimal outcomes are always possible. A fully experimental project (e.g. chasing a technology breakthrough) requires deliberate investment in an uncertain outcome — pharmaceutical companies may fail several formulas before succeeding. Some projects fail to deliver outcomes because the market opportunity passed or a competitor got there first. Effective project management minimizes negative outcomes, but the possibility remains part of the uncertainty of producing something unique.
Outcome → Check table (Delivery)
Projects contribute to business objectives Business plan + strategic plan + authorizing documents demonstrate alignment.
Projects realize the outcomes they were initiated to deliver Business case and underlying data show the project is still on track.
Benefits realized in planned time frame Benefits realization plan, business case, schedule show financial metrics/deliveries on track.
Team has clear understanding of requirements Predictive: little change in initial requirements. Evolving: clarity may not emerge until well into the project.
Stakeholders accept & are satisfied Interviews, observation, end-user feedback; complaint/return levels.
PDF page 66The delivery performance domain.
Part 1.2 § 1.2·08 — DOMAIN 7

Measurement Performance Domain

Addresses activities and functions associated with assessing project performance and taking appropriate actions to maintain acceptable performance.

"The value of measurements is not in the collection and dissemination of the data, but rather in the conversations about how to use the data to take appropriate action." Only measure what matters.
Metric
A description of a project or product attribute and how to measure it (e.g. work progress %).
Baseline
The approved version of a measure used as a basis for comparison to actual results (cost, duration).
Dashboard
A set of charts and graphs showing progress or performance against important project measures.
Memory hook
"Leading looks forward. Lagging looks back."
Leading indicators (proactive) predict changes/trends — e.g. rate of scope change requests, team workload balance. Lagging indicators (reactive) measure deliverables/events after the fact — e.g. cost variance, deliverables completed, customer satisfaction scores.
SMART criteria for effective metrics
S
Specific
M
Meaningful
A
Achievable
R
Relevant
T
Timely

Measuring takes time and effort that could otherwise go into productive work — so teams should only measure what's relevant and useful.

Why measure?
  • Evaluating performance vs. plan
  • Tracking resource utilization / work completed / budget expended
  • Demonstrating accountability
  • Providing information to stakeholders
  • Assessing whether deliverables are on track for benefits
  • Focusing conversations on trade-offs, threats, opportunities, options
  • Ensuring deliverables will meet customer acceptance criteria
WHAT TO MEASURE — SEVEN CATEGORIES
Category Examples
Deliverable Errors/defects, measures of performance, technical performance measures
Delivery Work in progress, lead time, cycle time, process efficiency
Baseline performance Start/finish dates, effort & duration, schedule variance
Resources Planned vs. actual resource utilization & cost
Business value Cost-benefit ratio, ROI, Net Present Value (NPV)
Stakeholders Net Promoter Score (NPS), mood chart, morale, turnover
Forecasts Estimate to Complete (ETC), Estimate at Completion (EAC), Variance at Completion (VAC)
Presenting information

Dashboards: status summaries (schedule/resources/budget with color-coded status: on track, complete, concern, issue, on hold, canceled, not started).
Information radiators: burndown charts (work remaining), burnup charts (work completed), combined burn charts (both at once), plus risk logs.
Visual controls: task boards, burn charts, cycle time / lead time tracking.

Cycle time vs. lead time
Cycle time: from the moment you start a task until you complete it.
Lead time: from the moment you put the item on the board until you deliver it — can be unpredictable since items in "Ready" can be reordered.
Outcome → Check table (Measurement)
Reliable understanding of project status Audit measurements/reports show if data is reliable.
Actionable data for decision making Measurements indicate whether performance is as expected or shows variance.
Timely, appropriate actions to stay on track Leading indicators and/or current status lead to timely decisions.
Achieving targets via reliable forecasts Comparing past forecasts to present performance, and planned vs. actual, shows likelihood of realizing intended value.
PDF page 73The measurement performance domain.
PDF page 82A stakeholder and team health dashboard.
PDF page 84Presenting information: dashboards.
PDF page 85Presenting information: information radiators.
PDF page 86Presenting information: visual controls and task boards.
Part 1.2 § 1.2·09 — DOMAIN 8

Uncertainty Performance Domain

Addresses activities and functions associated with risk and uncertainty.

Memory hook
"Uncertainty is the umbrella. RAC-V hides under it: Risk, Ambiguity, Complexity, Volatility."
Uncertainty (broadest): not knowing / unpredictability. Risk: not knowing future events. Ambiguity: not being aware of current/future conditions. Complexity: dynamic systems with unpredictable outcomes. Volatility: rapid, unpredictable change.
Uncertainty
A lack of understanding and awareness of issues, events, paths to follow, or solutions to pursue.
Ambiguity
A state of being unclear, having difficulty identifying the cause of events, or having multiple options to choose from.
Complexity
A characteristic of a program/project/environment that's difficult to manage due to human behavior, system behavior, and ambiguity.
Volatility
The possibility for rapid and unpredictable change.
Risk
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more objectives.
Two categories of ambiguity
Conceptual ambiguity: lack of effective understanding — occurs when people use similar terms/arguments differently. Example: "The schedule was reported on track last week" — is the schedule on track, or was it reported last week?

Situational ambiguity: surfaces when more than one outcome is possible — having multiple options to solve a problem is a form of it.
Working with complexity — 3 approaches
Systems-based Decoupling (disconnect parts to simplify + reduce connected variables); Simulation (learn from similar unrelated scenarios).
Reframing Diversity (view from diverse perspectives, brainstorm, Delphi-like convergence); Balance (mix forecasting + lagging data so variations counteract each other).
Process-based Iterate (build incrementally, learn each cycle); Engage (build in stakeholder engagement to reduce assumptions); Fail safe (build redundancy / graceful degradation for critical elements).
Volatility occurs from ongoing fluctuations in available skill sets or materials and usually impacts cost and schedule. Addressed via alternatives analysis (different skill mixes, resequencing work, outsourcing) and using cost/schedule reserve to cover overruns from price volatility.
RISK — THREATS & OPPORTUNITIES

Negative risks are called threats; positive risks are called opportunities. All projects have risk since they're unique undertakings with varying degrees of uncertainty. Overall project risk is often a function of complexity, ambiguity, and volatility together — responses apply to the whole project, not one event; if overall risk is too high, the organization may cancel the project.

Memory hook — threat strategies
"All Elephants Take Milk, Always." (AETMA)
Avoid → Escalate → Transfer → Mitigate → Accept
A
Avoid
Eliminate the root cause so it cannot occur
E
Escalate
Take to a higher power; manage outside the project
T
Transfer
Move to a group better able to manage it (e.g. insurance)
M
Mitigate
Take actions to reduce probability or impact
A
Accept
Take no action, but create a contingency reserve
Memory hook — opportunity strategies
"Every Elephant Shares Enough Apples." (EESEA)
Exploit → Escalate → Share → Enhance → Accept
E
Exploit
Ensure the opportunity is realized; assign best talent, prioritize the work
E
Escalate
Take to a higher power; manage outside the project
S
Share
Transfer to a 3rd party / spin up a group to ensure value is captured
E
Enhance
Increase probability or impact — e.g. add resources
A
Accept
Take no action, but promote and encourage
Reserves
Contingency reserve: set aside to address identified risks should they occur.
Management reserve: a budget category for unknown events, such as unplanned in-scope work.
Risk review

A frequent rhythm of review and feedback from a broad set of stakeholders helps navigate risk proactively. Daily standups can surface potential threats and opportunities; reports of blockers can become threats if they keep delaying progress; reports of breakthroughs may point to opportunities worth leveraging. Frequent demos of increments, interim designs, or proof-of-concepts also surface both.

Outcome → Check table (Uncertainty)
Awareness of the environment (technical/social/political/market/economic) The team incorporates environmental considerations when evaluating uncertainty, risks, and responses.
Proactively exploring and responding to uncertainty Risk responses align with the prioritization of constraints (budget/schedule/performance).
Awareness of interdependence of variables Actions addressing complexity, ambiguity, and volatility are appropriate.
Capacity to anticipate threats/opportunities Systems for identifying, capturing, responding to risk are appropriately robust.
Little/no negative impact from unforeseen events Scheduled delivery dates are met; budget performance within threshold.
Opportunities realized Teams use established mechanisms to identify and leverage opportunities.
Reserves used effectively Teams proactively prevent threats, limiting reserve use.

Also in Part 1 · principles 9 (Complexity) and 10 (Risk)

PDF page 88The uncertainty performance domain.
PDF page 102The five strategies for dealing with threats.
PDF page 103How risk exposure falls over the life of a project.
PDF page 104The five strategies for dealing with opportunities.
PART 1.3 · 41 SLIDES

Tailoring, Models, Methods & Artifacts

Fitting the approach to the work, and the toolkit you tailor with.

Fit the approach to the work

Tailoring Models, Methods & Artifacts

Tailoring is the deliberate adaptation of the development approach, governance, processes, methods, and artifacts to a project’s context. The goal is “just enough” discipline to deliver value and manage risk—not maximum or minimum process.

ContextLifecycleMethodsArtifactsInspect & adapt
Part 1.3 1.3·01 · The case for tailoring

Every project has a different shape

Product

Novelty, complexity, safety, architecture, quality attributes, physical/software coupling.

Project

Size, duration, budget, dependencies, uncertainty, delivery cadence, procurement.

Organization

Culture, governance, policies, process assets, distributed structure, maturity.

Environment

Regulation, market volatility, technology change, sustainability, geopolitical constraints.

People

Skills, team size, location, autonomy, stakeholder access, trust and experience.

Guardrail: organizational standards, law, contracts, security, safety, and audit needs constrain tailoring. Removing a control requires an evidence-based replacement or explicit authorization.

Also in Part 1 · principle 7, Tailoring · Part 1 · internal vs external environment

PDF page 26The principles of project management that tailoring works within.
Part 1.3 1.3·02 · Tailoring sequence

Choose, adapt, then improve

Select the initial development approach
Predictive, adaptive, or hybrid; determine delivery cadence.
Tailor for the organization
Align with governance, policy, methods, and required controls.
Tailor for the project
Adjust processes, roles, methods, ceremonies, tools, and artifacts.
Implement ongoing improvement
Inspect outcomes and adapt when evidence or context changes.

Record consequential tailoring decisions, rationale, constraints, owner, and review point. This creates transparency and prevents “we have always done it this way” from becoming the process.

Also in Part 1.2 · predictive, hybrid, adaptive in detail

PDF page 13The tailoring process, step by step.
PDF page 14Selecting the initial development approach.
PDF page 15Assessing the organizational and project factors when tailoring.
Part 1.3 1.3·03 · Three building blocks

Model → method → artifact

Model · a way to think

A simplified representation that explains behavior or relationships: situational leadership, communication models, motivation models, conflict models, complexity frameworks, change models.

Method · a way to act

A means for accomplishing work: estimating, workshops, interviews, retrospectives, earned value analysis, root-cause analysis, prioritization, testing, planning poker.

Artifact · evidence or information

A template, document, deliverable, or visual: charter, backlog, roadmap, risk register, schedule, business case, requirements, burn chart, dashboard, lessons learned.

Memory hook: a model frames the situation, a method performs the work, and an artifact captures or communicates the result.

Example: uncertain product

Model: Cynefin/complexity. Methods: prototypes and experiments. Artifacts: hypotheses, experiment results, ordered backlog.

Example: regulated release

Model: stage-gate. Methods: traceability and formal reviews. Artifacts: approvals, test evidence, requirements matrix.

Example: distributed agile team

Model: adaptive lifecycle. Methods: asynchronous refinement and virtual reviews. Artifacts: shared backlog, decision log, definition of done.

PDF page 28Situational leadership models.
PDF page 29Motivational models.
PDF page 30Change models, including ADKAR.
PDF page 31Complexity models.
PDF page 32Team development models.
PDF page 34Commonly used methods, by performance domain.
PDF page 39Commonly used artifacts, by performance domain.
Part 1.3 1.3·04 · Design tests

Evaluate the tailored system

Value

Does this activity or artifact improve a decision, reduce risk, enable delivery, or satisfy a real obligation?

Sufficiency

Is the evidence detailed enough for its audience and consequence—without avoidable duplication?

Coherence

Do roles, cadence, governance, lifecycle, methods, and tools reinforce one another?

Feedback speed

How quickly does the approach expose incorrect assumptions, defects, and changing needs?

Adoption

Can the team actually use it? A theoretically perfect process that people bypass is not effective.

Compliance

Are mandatory policy, contractual, regulatory, safety, security, and audit needs demonstrably met?

Review at retrospectives, phase gates, releases, major risk events, team changes, and shifts in external conditions. Use outcomes—cycle time, defects, rework, value, risk exposure—not document count.

PDF page 21Situations and the tailoring each one suggests.
Part 1.3 §1.3·07 — FROM THE SLIDES

The lists the slides test you on

The breakdown above explains tailoring in practice; these are the exact lists from the Chapter 1.3 deck.

Slide topic What to remember
Definition Deliberate adaptation of the PM approach, governance and processes to the environment and the work at hand.
Why tailor (3) More commitment from team members who helped tailor · customer-oriented focus · more efficient use of resources.
What to tailor (5) Life cycle and development approach · processes (added, modified, removed, blended, aligned) · engagement (people, empowerment, integration) · tools · methods and artifacts.
Tailoring process (4) Select initial approach → tailor for the organization → tailor for the project → implement ongoing improvement.
Tailoring for the project Product/deliverable: compliance/criticality, type, industry market, technology, time frame, stability of requirements, security. Project team: size, geography, organizational distribution, experience, access to customer. Culture: buy-in, trust, empowerment, organizational culture.
Situation → suggestion Poor quality → feedback loops and QA. Team unsure → guidance, training, verification. Approval delays → fewer approvers up to value thresholds. Too much WIP/scrap → value stream mapping, kanban. Disengaged stakeholders → deeper engagement. No visibility → collect and discuss measures. Surprise issues → root causes.
Model families Situational leadership (Situational Leadership II, OSCAR) · communication (cross-cultural, channel effectiveness, gulf of execution and evaluation) · motivational (hygiene vs motivators, intrinsic vs extrinsic, hierarchy of needs, Theory X/Y/Z) · change (ADKAR, 8-step process, Satir, Transition) · complexity (Cynefin, Stacey matrix) · team development (Tuckman, Drexler/Sibbet) · other (conflict, negotiation, planning, process groups, Salience).
Method categories Data gathering and analysis · estimating · meetings and events · other.
Artifact categories Strategy · logs and registers · plans · hierarchy charts · baselines · visual data · reports · agreements and contracts · other.
Avoid anything that Duplicates effort · isn't useful · gives incorrect or misleading information · caters to individual over team needs.
ALL OF CHAPTER 1

Review: mistakes, cheat sheets, quizzes, labs

Everything from the three parts grouped by type, each tagged with the part it came from.

Part 1 § 09 — COMMON MISTAKES

Where students actually lose points

These are the specific mix-ups this chapter sets up — drill these before anything else.

1. Portfolio vs. Program vs. Project
✗ WRONG — "A program is just a big project."
✓ RIGHT — A project is temporary with a defined end; a program is related projects/programs managed together for benefits not available managing them individually; a portfolio is projects/programs/portfolios/operations grouped for strategic objectives. Scope grows: project → program → portfolio.
2. Product vs. Project
✗ WRONG — Using "product" and "project" interchangeably.
✓ RIGHT — A project is a temporary endeavor; a product is a quantifiable artifact that's produced (an end item or component). A project can produce a product, but the words describe different things — temporary effort vs. tangible output.
3. The 12 Principles vs. the 8 Performance Domains
✗ WRONG — Listing "Risk" as one of the 8 Performance Domains.
✓ RIGHT — Risk is one of the 12 Principles. The closest domain is "Uncertainty." Principles = guidelines for behavior; Domains = areas of work you actively manage.
4. PMP® vs. CAPM®
✗ WRONG — Thinking students should pursue the PMP® directly.
✓ RIGHT — PMP® (Project Management Professional) targets experienced practitioners. Students join PMI at a reduced fee and pursue the CAPM® (Certified Associate in Project Management) — the entry-level cert.
5. Internal vs. External environment factors
✗ WRONG — Listing "regulatory environment" or "industry standards" as internal factors.
✓ RIGHT — Regulatory environment, industry standards, marketplace conditions, and social/cultural influences are external. Process assets, governance documentation, and internal knowledge/infrastructure are internal. Rule of thumb: could a factor exist without your organization? If yes, it's external.
6. Centralized vs. decentralized coordination
✗ WRONG — "Decentralized" means there's no leadership at all.
✓ RIGHT — Decentralized coordination means the team self-organizes and self-manages (no single designated PM role driving it); centralized coordination means a designated project manager leads. A centralized project can still include self-organized sub-teams for parts of the work — the two aren't mutually exclusive.
7. Outcome vs. Benefit vs. Value — order of the chain
✗ WRONG — "Value creates outcomes."
✓ RIGHT — The direction is fixed: Component → Deliverable → Outcome → Benefit → Value. Outcomes are the end result; outcomes create benefits (organizational gains); benefits create value (worth/importance/usefulness).
8. Principles vs. Code of Ethics
✗ WRONG — Treating the 12 principles and the 4 ethics values as the same list.
✓ RIGHT — The 12 Principles (Stewardship, Team, Stakeholders, Value…) guide PM behavior broadly and are not necessarily moral. The PMI Code of Ethics and Professional Conduct is a separate, four-value set — Responsibility, Respect, Fairness, Honesty — specifically about moral conduct, required to earn the PMP®.
Part 1.2 § 11 — COMMON MISTAKES

What students actually get wrong on this chapter

Eight domains that sound similar in places — here's where the exam traps live.

Accuracy vs. Precision

✗ WRONG"The estimate was precise, so it must be accurate."
✓ RIGHTPrecision (exactness/detail) and accuracy (correctness) are independent. A precise, detailed cost breakdown can still be way off from actual cost.
Why it's tested: they're both about "how good is the estimate," which makes them feel synonymous — but PMBOK deliberately splits them.

Contingency Reserve vs. Management Reserve

✗ WRONGTreating them as interchangeable "extra budget."
✓ RIGHTContingency reserve = for identified/known risks, usually controlled by the PM. Management reserve = for unknown, in-scope, unplanned work, usually controlled by upper management/sponsor/PMO.
Why it's tested: "known vs. unknown risk" and "PM-controlled vs. management-controlled" are the two axes that distinguish them — memorize both.

Leadership vs. Management

✗ WRONG"Management can be distributed but leadership can't" — or the reverse.
✓ RIGHTLeadership activities should be practiced by ALL project team members, regardless of structure. Management activities MAY be centralized or distributed.
Why it's tested: it's tempting to assume both scale the same way — they don't. Leadership is universal; management structure is a choice.

Threat strategies vs. Opportunity strategies

✗ WRONGUsing "Mitigate" for a positive risk, or "Enhance" for a negative one.
✓ RIGHTThreats (negative): Avoid, Escalate, Transfer, Mitigate, Accept. Opportunities (positive): Exploit, Escalate, Share, Enhance, Accept. Only Escalate and Accept are shared between the two lists.
Why it's tested: four of the five terms per list sound like they could apply to either — the exam checks whether you know which list a term belongs to.

Leading vs. Lagging indicators

✗ WRONGAssuming "cost variance" is a leading indicator because it "leads to decisions."
✓ RIGHTLeading = proactive, predicts future trends (e.g. rate of scope change requests). Lagging = reactive, reports on what already happened (e.g. cost variance, deliverables completed).
Why it's tested: "leading to action" and "leading indicator" sound related but aren't — a lagging indicator absolutely can trigger action, it's just measuring the past.

Conceptual vs. Situational ambiguity

✗ WRONGTreating "multiple valid options to solve a problem" as conceptual ambiguity.
✓ RIGHTConceptual ambiguity = a misunderstanding from unclear language/terms (e.g. an ambiguous sentence). Situational ambiguity = more than one possible outcome/option actually exists in the situation itself.
Why it's tested: one is about unclear communication, the other is about unclear reality — easy to conflate.

RFI vs. RFP vs. RFQ

✗ WRONGUsing "RFP" whenever any vendor document is mentioned.
✓ RIGHTRFI = "what's out there?" (exploring options). RFP = "bid on building this specific thing." RFQ = "give me your price/timeline for this exact, well-defined item."
Why it's tested: the exam gives you a scenario and expects you to match it to the right stage of the bid process.

Complexity's three approaches: Systems-based, Reframing, Process-based

✗ WRONGMixing up which technique (decoupling, diversity, iterate) belongs to which category.
✓ RIGHTSystems-based = decoupling, simulation. Reframing = diversity, balance. Process-based = iterate, engage, fail safe.
Why it's tested: three parallel lists of similar-sounding tactics is a classic matching-question setup.
Part 1.3 05 · Common traps

Tailoring is not permission to drift

Copy-paste process

A prior project is evidence, not a universal recipe. Reassess its assumptions.

Method buffet

Combining fashionable practices without understanding interfaces creates friction.

Zero documentation

“Agile” does not erase knowledge-transfer, compliance, architecture, or operating needs.

Permanent first choice

The initial approach is a hypothesis. Update it when results or context disagree.

Part 1 § 10 — CHEAT SHEET

Chapter 1, in three tables

Nested scope, small → large
Term One-line definition
Product A quantifiable artifact produced — an end item or component.
Project A temporary endeavor to create a unique product, service, or result.
Program Related projects/programs managed together for benefits not available individually.
Portfolio Projects, programs, subsidiary portfolios, and operations grouped for strategic objectives.
12 Principles, condensed
# Principle One-line gist
1 Stewardship Act responsibly and ethically.
2 Team Foster trust, respect, open communication.
3 Stakeholders Involve stakeholders proactively.
4 Value Prioritize outcomes that deliver value.
5 Systems Thinking Understand interactions within/beyond the project.
6 Leadership Lead with integrity, adaptability, empathy.
7 Tailoring Adapt methods, tools, and approaches.
8 Quality Embed quality from the start.
9 Complexity Embrace uncertainty and complexity.
10 Risk Identify, assess, and respond to risks.
11 Adaptability & Resiliency Be flexible and ready to pivot.
12 Change Support transformation and continuous improvement.
8 Performance Domains
# Domain
1 Stakeholders
2 Team
3 Development Approach and Life Cycle
4 Planning
5 Project Work
6 Delivery
7 Measurement
8 Uncertainty
Part 1.2 § 10 — CHEAT SHEET

All 8 domains in one table

# Domain Addresses Signature term / idea
1 Stakeholders Activities/functions associated with stakeholders Stakeholder analysis; the 3-ring map
2 Team People producing deliverables Management vs. leadership; centralized vs. distributed
3 Development Approach & Life Cycle Development approach, cadence, life cycle phases Predictive / hybrid / adaptive
4 Planning Initial/ongoing/evolving org & coordination Accuracy vs. precision; dependencies
5 Project Work Processes, physical resources, learning RFI / RFP / RFQ; explicit vs. tacit knowledge
6 Delivery Scope & quality the project was chartered to achieve Definition of Done; Cost of Quality
7 Measurement Assessing performance, taking action Leading vs. lagging indicators; SMART
8 Uncertainty Risk and uncertainty Risk/Ambiguity/Complexity/Volatility; AETMA / EESEA
Part 1 § 11 — POP QUIZ

Click a question to reveal the answer

Quick self-check, separate from the Practice Lab below.

MC · What project is most often cited as the first to use "modern" project management?
The Manhattan Project (led by Dr. Oppenheimer) — a three-year, $2 billion (1946 dollars) project that had a separate project manager and technical manager.
Short answer · What are the four values in the PMI Code of Ethics and Professional Conduct?
Responsibility, Respect, Fairness, and Honesty.
MC · Which of these is not one of the 8 Project Performance Domains: Stakeholders, Risk, Planning, Delivery?
Risk. Risk is one of the 12 Principles, not a Performance Domain. The related domain is "Uncertainty."
Short answer · Put in order: Component, Value, Outcome, Benefit.
Component → Outcome → Benefit → Value. (Components create deliverables that produce outcomes; outcomes create benefits; benefits create value.)
MC · Which type of coordination has project team members self-organize and self-manage?
Decentralized coordination. Centralized coordination instead relies on the leadership and guidance of a designated project manager or similar role.
Short answer · Why did companies start creating PMOs in the 1990s?
To help handle the increasing number and complexity of projects — a PMO is an organizational unit responsible for coordinating the project management function throughout an organization.
MC · Per PMI's Pulse of the Profession® report, how much do organizations waste for every $1 billion spent on projects?
$97 million.
Short answer · Name the three forms product management can take relative to programs and projects.
1) Program management within a product life cycle, 2) Project management within a product life cycle, 3) Product management within a program.
Part 1.2 § 12 — POP QUIZ

Click a question to reveal the answer

Self-check before the Practice Lab. No reload, no scrolling away.

MCQ
1. Which performance domain addresses "activities and functions associated with the development approach, cadence, and life cycle phases of the project"?
Answer: Development Approach and Life Cycle Performance Domain — this is its exact textbook definition.
Short answer
2. A team estimates a project will cost $100K and it ends up costing $102K. Was the estimate accurate, precise, both, or neither — and why?
Answer: Accurate — it's a close prediction of reality (correctness). Whether it was also precise depends on whether it was built from a detailed, consistent cost breakdown, which is a separate question from whether the final number was close.
MCQ
3. A project team self-organizes with no designated project manager; someone within the team serves as facilitator, and this role shifts among members. Is this centralized or distributed management?
Answer: Distributed management and leadership — accountability is shared rather than assigned to one individual.
Short answer
4. Name the four types of schedule dependencies.
Answer: Mandatory, Discretionary, External, Internal.
MCQ
5. A time-and-materials subcontractor finishes early, saving cost and schedule. Which of the five opportunity strategies best fits "reassigning your best talent to make sure this keeps happening"?
Answer: Exploit — ensuring the opportunity is realized by assigning best talent and prioritizing the work.
Short answer
6. What's the difference between a leading and a lagging indicator? Give one example of each.
Answer: Leading indicators are proactive and predict future trends (e.g. rate of scope change requests). Lagging indicators are reactive and report after the fact (e.g. cost variance).
MCQ
7. A company issues a document to learn what vendor capabilities exist before deciding what to buy. Is this an RFI, RFP, or RFQ?
Answer: Request for Information (RFI) — used to explore options before a decision has been made.
Short answer
8. What is the "last responsible moment," and which planning approach uses it?
Answer: Deferring a decision to allow the team to consider multiple options until the cost of further delay would exceed the benefit. It's used in iterative/incremental planning for routine work.
Part 1.3 06 · Retrieval practice

Check your reasoning

What is the difference between tailoring and a hybrid approach?
Tailoring adapts the whole project approach to context. Hybrid specifically combines predictive and adaptive elements; it is one possible tailoring outcome.
Classify a risk register: model, method, or artifact?
Artifact. It captures and communicates risk information.
When should tailoring decisions be revisited?
Continuously, especially at retrospectives, phase or release boundaries, major changes, and when performance evidence shows the approach is not working.
A team wants to remove a mandatory security review because it slows delivery. What should happen?
Confirm the constraint and seek an authorized, evidence-based alternative that preserves the control objective; do not silently remove it.
Part 1 § 12 — PRACTICE LAB

Apply the definitions to real scenarios

Same shape of question this chapter's terminology gets tested with — grounded directly in the slide definitions.

1. A university runs three related efforts together — a new LMS rollout, a campus-wide Wi-Fi upgrade, and a digital ID system — coordinated as a group because managing them together unlocks efficiencies none of them would get alone. What is this grouping called?
→ A Program
Why: a program is related projects (and subsidiary programs/activities) managed in a coordinated manner to obtain benefits not available from managing them individually.
2. A company chooses which of its many projects, programs, and ongoing operations to fund this year based on which best serve its strategic objectives. What PMBOK term names that top-level grouping?
→ A Portfolio
Why: a portfolio is projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
3. A six-month effort to build and launch a new mobile app has a clear start date and a clear end date, and produces one unique deliverable. What is it?
→ A Project
Why: a project is a temporary endeavor undertaken to create a unique product, service, or result — temporary nature means a defined beginning and end.
4. A project team ships a feature (the outcome), which increases user retention (the organizational gain). What PMBOK term describes "increased user retention" here, and what does that in turn create?
→ A Benefit, which creates Value
Why: outcomes create benefits — gains realized by the organization. Benefits, in turn, create value — something of worth, importance, or usefulness.
5. A project team member proposes tailoring the schedule cadence differently from how it was done last quarter because this project's team, deliverables, and stakeholders are different. Which principle does this best illustrate?
→ Tailoring
Why: each project is unique — tailoring means designing the development approach using "just enough" process to fit the project's own context, and it's an iterative, continuous process throughout the project.
Part 1.2 § 13 — PRACTICE LAB

Scenario → domain / concept → why

Exam-style scenario questions grounded directly in the slide content.

1. A project manager reviews the risk register and issue register, and runs a stakeholder survey, to determine whether project beneficiaries are satisfied and whether any opponents are negatively affecting outcomes. Which performance domain is this activity part of?
→ Stakeholder Performance Domain
Why: surveys, interviews, focus groups, and reviewing the issue/risk register are the specific "checks" listed for the outcome "beneficiaries are supportive and satisfied."
2. A team estimates a construction project's cost, schedule, and resource needs almost entirely upfront, because the investment is large and any change requires a formal change-control process and replanning between phases. Which development approach is this, and why?
→ Predictive (waterfall)
Why: requirements can be defined/collected/analyzed at the start; used when there's significant investment and high risk requiring frequent reviews and change control — the textbook description of the predictive approach.
3. A budget of $500K in work-cost estimates is aggregated into a cost baseline of $520K after adding reserve for identified risks controlled by the PM. Which reserve type was just added, and what would be added next to reach the full project budget?
→ Contingency reserve was added; Management reserve comes next.
Why: Work Cost Estimates → + Contingency Reserve = Cost Baseline → + Management Reserve = Project Budget, per the budget build-up chain.
4. A subcontractor's schedule slips repeatedly because of fluctuating material prices and availability of skilled labor. The team responds by evaluating outsourcing part of the work and drawing on a cost reserve to absorb the price swings. Which aspect of uncertainty is being addressed, and how?
→ Volatility, addressed via alternatives analysis and reserve.
Why: volatility = ongoing fluctuations in available skill sets or materials, usually impacting cost/schedule — addressed by alternatives analysis (outsourcing, resequencing) and cost/schedule reserve.
5. A team notices that "the schedule was reported on track last week" is confusing everyone in a status meeting — some read it as the schedule being on track, others as merely having been reported. What type of ambiguity is this, and what's the other type?
→ Conceptual ambiguity (the other type is situational ambiguity)
Why: conceptual ambiguity is a lack of effective understanding from people using similar terms differently; situational ambiguity instead surfaces when more than one real-world outcome is possible.