SE423 // MIDTERM · CH 1–3
SE423 · Software Project Management · Midterm

Chapters 1–3, everything on one page

Every definition, list, table and comparison from the five midterm decks, the hooks that make them stick, and a practice exam graded by keywords. The image-only slides (principle cards, checking-outcome tables, power types, RACI) are written out here too.

  1. Read the summary once, top to bottom. Highlighted words are the keywords the grader looks for.
  2. Cover the lists in Memorize and recall them before tapping to reveal.
  3. Take the practice exam, then use "Retry missed" until every chapter bar is full.

Summary

Slide order, nothing skipped. Chapter 2 excludes the slides that were cancelled.

CH 1

Introduction

PM basics · history · project managers · PMBOK v7 · value delivery · principles

DEFProject management

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements. It guides the project work to deliver the intended outcomes.

Teams can use a broad range of approaches: predictive, hybrid, adaptive.

NUMBERSWhy PM matters background, not tested

  • By 2027, employers need 87.7 million people in PM-oriented roles (PMI).
  • 2.3 million new PM employees needed each year to 2030 (PMI 2021 Talent Gap).
  • Organizations waste $97 million per $1 billion spent on projects (PMI Pulse of the Profession).
  • Top graduate skills are all PM-related: teamwork, problem-solving, verbal communication.
  • Saudi Smart Government Strategy: AI market to $135.2 B by 2030, 12.4% of GDP.
  • Saudi tech spending ≈ $24.7 B (SR 93 B) in 2025, highest in the world, 21.7% of national spending.

HISTORYProject management history

  • Some argue the Egyptian pyramids and the Great Wall of China were projects.
  • The Manhattan Project (led by Oppenheimer) is considered the first to use "modern" PM: 3 years, $2 billion (1946 dollars), with a separate project manager and technical manager.
  • In the 1990s companies began creating PMOs for the growing number and complexity of projects.
DefA Project Management Office (PMO) is an organizational unit responsible for coordinating the project management function throughout an organization.

4Global issues forcing organizations to rethink

  1. Talent development for project and program managers is a top concern
  2. Basic PM techniques are core competencies
  3. Organizations want more agile approaches
  4. Benefits realization of projects is a key metric

PMICertification and ethics

  • PMI (Project Management Institute) leads the profession and awards the PMP® (Project Management Professional).
  • Students can join at a reduced fee and earn the CAPM (Certified Associate in Project Management).
  • Ethics: a set of principles that guide decision making based on personal values of "right" and "wrong". PMs often face ethical dilemmas.
  • PMP applicants must agree to PMI's Code of Ethics and Professional Conduct; several exam questions cover professional responsibility.
HookCode of Ethics = 4 values: Responsibility, Respect, Fairness, Honesty. "Real Respect For Honesty".

PMProject managers

Mainly responsible for all issues related to the software project. Common issues:

ScheduleBudgetQualityDelivery of productsLocking in resources

Most of a PM's time is consumed chasing and collecting the status of project tasks.

97% of successful projects were led by experienced PMs.

Skills: be comfortable with change · understand the organizations they work in and with · be able to lead teams to accomplish goals.

14Competencies for project managers

  1. People skills
  2. Leadership
  3. Listening
  4. Integrity, ethical behavior, consistent
  5. Strong at building trust
  6. Verbal communication
  7. Strong at building teams
  8. Conflict resolution / management
  9. Critical thinking, problem solving
  10. Understands, balances priorities
  11. Negotiating
  12. Influencing the organization
  13. Mentoring
  14. Process and technical expertise

10Advantages of formal project management

  1. Better control of financial, physical, human resources
  2. Improved customer relations
  3. Shorter development times
  4. Lower costs, improved productivity
  5. Higher quality, increased reliability
  6. Higher profit margins
  7. Better internal coordination
  8. Positive impact on meeting strategic goals
  9. Higher worker morale (less stress)
  10. Less overworked personnel

PMBOKThe Standard for Project Management

Provides a basis for understanding PM and how it enables intended outcomes. Applies regardless of industry, location, size, or delivery approach (predictive, hybrid, adaptive).

It describes the system projects operate in: governance, possible functions, the project environment, and the relationship between project management and product management.

12Project management principles (PMBOK v7): name, statement, key points

Hook"Stewards Trust Stakeholders' Value; Systems Leaders Tailor Quality, Complexity, Risk, Adapt & Change."
# Principle Statement (slide 58) What the card says
1 Stewardship Be a diligent, respectful, and caring steward Act responsibly with integrity, care, trustworthiness, compliance; responsibilities inside and outside the organization; holistic view (financial, social, technical, environmental).
2 Team Create a collaborative project team environment Projects are delivered by teams; teams often build a "local" culture; collaboration aligns cultures, enables learning, optimizes contribution.
3 Stakeholders Effectively engage with stakeholders Engage proactively and to the degree needed; stakeholders influence projects, performance and outcomes; engagement advances value delivery.
4 Value Focus on value Value is the ultimate indicator of project success; realized during the project, at the end, or after; quantitative or qualitative; focus on outcomes.
5 Systems thinking Recognize, evaluate, and respond to system interactions A project is a system of interdependent domains; holistic view of how parts interact internally and externally; systems keep changing.
6 Leadership Demonstrate leadership behaviors Leadership is different than authority; any team member can lead; effective leaders adapt style to the situation; model honesty, integrity, ethics.
7 Tailoring Tailor based on context Each project is unique; use "just enough" process; tailoring is iterative and continuous; maximize value, manage cost, enhance speed.
8 Quality Build quality into processes and deliverables Satisfy stakeholder expectations and requirements; meet acceptance criteria; processes appropriate and effective.
9 Complexity Navigate complexity Complexity comes from human behavior, system interactions, uncertainty, ambiguity; can emerge at any point; stay vigilant.
10 Risk Optimize risk responses Risks can be opportunities or threats; responses must be appropriate, cost effective, realistic, agreed to by stakeholders, owned by a person.
11 Adaptability & resiliency Embrace adaptability and resiliency Adaptability = respond to changing conditions. Resiliency = absorb impacts and recover quickly from a setback. Focus on outcomes, not outputs.
12 Change Enable change to achieve the envisioned future state Structured change moves people from current to future state; change can be internal or external; too much change too fast causes change fatigue/resistance.

RULESAbout the principles

  • Guidelines for strategy, decision making and problem solving.
  • Not prescriptive (unlike laws/rules in some professions); they guide behavior.
  • Broadly based, so there are many ways to stay aligned.
  • Can, but do not necessarily, reflect morals. A code of ethics is what relates to morals.
  • Application depends on context (organization, project, team, stakeholders...).
  • Internally consistent: no principle contradicts another, though practical dilemmas can arise.
  • They overlap with general management principles (both focus on delivering value).

8Project performance domains (preview)

Key areas of focus that must be managed effectively to achieve successful outcomes.

  1. Stakeholders
  2. Team
  3. Development Approach & Life Cycle
  4. Planning
  5. Project Work
  6. Delivery
  7. Measurement
  8. Uncertainty
Hook"Smart Teams Develop Plans, Produce Deliverables, Measure Uncertainty."

TERMSKey terms and concepts

Term Definition Remember
Outcome An end result or consequence of a process or project. Broader than outputs: focuses on the benefits and value.
Portfolio Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. E.g. a company's R&D programs, marketing campaigns.
Program Related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually. E.g. a company-wide digital transformation.
Project A temporary endeavor undertaken to create a unique product, service, or result. Temporary = has a beginning and an end. Can stand alone or be part of a program/portfolio.
Product An artifact that is produced, is quantifiable, and can be an end item or a component item.
Project manager The person assigned by the performing organization to lead the team responsible for achieving the project objectives. Facilitates team work and manages processes.
Project team A set of individuals performing the work of the project to achieve its objectives.
Project management team Members of the project team directly involved in PM activities. A subset of the project team.
System for value delivery A collection of strategic business activities aimed at building, sustaining, and/or advancing an organization. Portfolios, programs, projects, products, operations can all be part of it.
Value The worth, importance, or usefulness of something. Customers: features/functions. Organizations: business value (benefits minus cost). Society: contribution to people, communities, environment.

SYSTEMA system for value delivery provides

  • How to create value: how projects operate within a system to produce value.
  • Organizational governance system: how governance supports value delivery (policies, performance monitoring).
  • Functions associated with projects.
  • The project environment: internal and external factors.
  • Product management considerations: how portfolios, programs, projects and products relate.

5Ways projects create value

  1. Creating a new product, service, or result that meets customer/end-user needs
  2. Creating positive social or environmental contributions
  3. Improving efficiency, productivity, effectiveness, or responsiveness
  4. Enabling the changes needed for organizational transition to its desired future state
  5. Sustaining benefits enabled by previous programs, projects, or operations

CHAINValue delivery components

Portfolios, programs, projects, products and operations, used individually or together, form a system aligned with strategy. Operations (payroll, supply chain, HR, finance...) support and influence them.

Components→Deliverables→Outcomes→Benefits→Value

The value system sits in the internal environment (policies, procedures, governance) inside the external environment (economy, competition, legislation).

FLOWInformation flow

  • Senior leadership → portfolios: strategic information.
  • Portfolios → programs and projects: desired outcomes, benefits, value.
  • Programs/projects → operations: deliverables + support and maintenance info.
  • Operations → programs/projects: adjustments, fixes, updates to deliverables.
  • Programs/projects → portfolios: performance and progress on outcomes, benefits, value.
  • Portfolios → senior leadership: evaluations of portfolio performance.
  • Operations → leadership: how well strategy is advancing.

GOVOrganizational governance systems

  • Work alongside the value delivery system to enable smooth workflows, manage issues, support decision making.
  • Framework elements: oversight, control, value assessment, integration among components, decision-making.
  • Integrated structure for evaluating changes, issues and risks.
  • Project governance defines the authority to approve changes and make business decisions; aligned with program/organizational governance.
  • A PMO might support programs and projects within a portfolio.

COORDFunctions associated with projects

People drive project delivery. Functions can be filled by one person, a group, or combined roles.

  • Decentralized coordination: team members self-organize and self-manage.
  • Centralized coordination: leadership of a designated project manager.
  • Centralized projects can still use self-organized teams for portions of work.
  1. Provide oversight and coordination (monitoring progress)
  2. Present objectives and feedback (defining success criteria)
  3. Facilitate and support (hosting meetings, stand-ups)
  4. Perform work and contribute insights (completing deliverables)
  5. Apply expertise (advising on technical matters)
  6. Provide business direction and insight (market trends)
  7. Provide resources and direction (allocating budget, people)
  8. Maintain governance (enforcing regulatory/internal standards)

ENVThe project environment

Influences can be favorable, unfavorable, or neutral.

Internal (from the organization, portfolio, program, another project): process assets · governance documentation · data assets · knowledge assets · security and safety · infrastructure · IT software · resource availability · employee capability.

External: marketplace conditions · social and cultural influences · regulatory environment · commercial databases · academic research · industry standards · financial considerations · physical environment.

PRODUCTProduct management considerations

Product management integrates people, data, processes, and business systems to create, maintain and develop a product through its life cycle.

Introduction→Growth→Maturity→Retirement

Three forms:

  1. Program management within a product life cycle: a set of programs and projects for complex phases (modernizing a product years after launch).
  2. Project management within a product life cycle: portfolio governance charters individual projects for enhancements (modernizing the UI).
  3. Product management within a program: the full product life cycle inside one program (building a POC).
CH 1.2

Project Performance Domains

8 domains · each has definitions, content, and an outcome → check table

DEFProject performance domain

A group of related activities that are critical for the effective delivery of project outcomes. Domains are interactive, interrelated, and interdependent, work in unison, and run concurrently throughout the project regardless of how value is delivered (frequently, periodically, at the end). The 12 principles guide behavior inside the domains.

1Stakeholder domain

Stakeholder
An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio.
Stakeholder analysis
Systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account. Includes internal/external, supportive, neutral and unsupportive stakeholders.
KeyInterpersonal and leadership skills are maybe more important than technical PM skills when working with stakeholders.
Outcome Check
Productive working relationship with stakeholders Observed; movement along a continuum of engagement shows satisfaction.
Stakeholder agreement with objectives Many changes to scope/requirements suggest stakeholders are not aligned.
Beneficiaries supportive; opponents don't hurt results Behavior, surveys, interviews, focus groups; issue and risk registers.

2Team domain

Management focuses on the means of meeting objectives (processes, planning, coordinating, measuring). Leadership focuses on people (influencing, motivating, listening, enabling). Both matter.

  • Centralized: accountability (being answerable for an outcome) assigned to one individual (the PM); a project charter authorizes the PM to form the team.
  • Distributed: PM activities shared among a PM team; teams may self-organize with a rotating facilitator instead of a designated PM.
Decentralized Centralized
Middle/low managers decide A few upper managers decide
Authority close to stakeholders Authority at the top of the chain
Self-sufficient units More standardization
Faster decisions More control
More expensive Less expensive
More creativity Limited creativity

2Team development and culture

Common aspects of team development: vision and objectives · roles and responsibilities · project team operations · guidance · growth.

Behaviors the PM models for a safe culture: transparency · integrity · respect · positive discourse · support · courage · celebrating success.

High-performing team factors: open communication · shared understanding · shared ownership · trust · collaboration · adaptability · resilience · empowerment · recognition.

Leadership skills: establishing and maintaining vision · critical thinking · motivation · interpersonal skills.

2Emotional intelligence and leadership styles

EI component Means
Self-awareness How do you affect the team, how does it affect you?
Self-management Think before you act; build trust.
Social awareness Be empathetic; active listening.
Social skill Rapport, build effective teams, manage attitude.

Styles (autocratic, democratic, laissez-faire, transactional, servant...) are tailored based on: experience with the project type · maturity of team members · organizational governance structures · distributed teams.

Check: shared ownership (all know the vision) · high-performing team (trust, adapt, empowered) · leadership and interpersonal skills demonstrated by all.

3Development approach & life cycle domain

Deliverable
Any unique and verifiable product, result, or capability to perform a service required to complete a process, phase, or project.
Development approach
Method used to create and evolve the product: predictive, iterative, incremental, adaptive, or hybrid.
Cadence
A rhythm of activities conducted throughout the project.
Project phase
Logically related activities that culminate in one or more deliverables.
Project life cycle
The series of phases from start to completion.
Deliverable type→Approach + cadence→Life cycle & phases

Delivery cadence = timing and frequency of deliveries: single, multiple, periodic. Continuous delivery = delivering feature increments immediately through small batches and automation (DevOps, #noprojects, Continuous Digital).

3Predictive vs hybrid vs adaptive

Approach Use it when
Predictive (waterfall) Requirements can be defined at the start; significant investment and high risk needing reviews and change control; scope, schedule, cost stable; reduces uncertainty early, planning upfront.
Hybrid Mix of adaptive and predictive; uncertainty or risk around requirements; deliverables can be modularized or built by different teams.
Adaptive (agile) Requirements highly uncertain and volatile; clear vision first, requirements refined from feedback; iterative and incremental; agile iterations of 1 to 2 weeks with a demo; team picks scope from a prioritized backlog.

Phase gate (stage gate) review checks the phase's exit criteria are met before moving on.

3Considerations for selecting an approach

Product/service (8): degree of innovation · requirements certainty · scope stability · ease of change · delivery options · risk · safety requirements · regulations.

Project (3): stakeholders (adaptive needs heavy involvement, e.g. product owner) · schedule constraints (deliver something early → iterative/adaptive) · funding availability (uncertain funding → adaptive; release an MVP).

Organization (4): structure · culture · capability · team size and location.

Check: approach consistent with deliverables · life cycle phases connect delivery from start to end · phases support the cadence.

4Planning domain: definitions

Estimate
Quantitative assessment of the likely amount or outcome of a variable (costs, resources, effort, durations).
Accuracy
Assessment of correctness: how well the plan predicts reality ($100K estimate, $102K actual = accurate).
Precision
Assessment of exactness: level of detail in the assumptions. Can be precise but not accurate.

Planning proactively develops an approach to create the deliverables. High-level planning can begin before authorization; teams progressively elaborate the vision statement, charter, business case. Increasingly includes social and environmental impacts (product life cycle assessment).

Product scope = features and functions. Project scope = the work performed to deliver them.

4Planning: delivery, schedules, dependencies

  • Predictive: decompose deliverables with a scope statement / WBS.
  • Iterative/incremental: themes/epics → features → user stories; tackle risky/novel work first.
  • Last responsible moment: defer a decision until the cost of delay would exceed the benefit.

Predictive schedule, 5 steps:

Decompose scope into activities→Sequence→Estimate effort, duration, resources→Allocate people→Adjust until agreed
Dependency Meaning Modify?
Mandatory Contractually required or inherent in the work Usually no
Discretionary Based on best practices or preferences May
External Project vs non-project activities Usually no
Internal Between project activities May

Adaptive scheduling: release plan → each release has 2+ iterations; future releases stay high level. Timeboxes pull from a prioritized backlog, team self-manages, demos at the end, backlog reprioritized.

4Planning: budget, resources, procurement, metrics

  • Cost estimates aggregate into the cost baseline (time-phased budget) spread over the schedule.
  • Contingency reserve: for identified risks, controlled by the PM.
  • Management reserve: for unknown/unexpected in-scope work, usually controlled by upper management (or sponsor, product owner, PMO).
Work cost estimates+Contingency=Cost baseline+Management reserve=Project budget
  • Physical resources: anything that is not a person (materials, equipment, software, licenses); plan lead time, storage, logistics.
  • Procurement: once high-level scope is known, do a make-or-buy analysis.
  • Metrics link planning, delivering and measuring; set thresholds; "only measure what matters."

Check: organized progress · holistic approach · evolving info elaborated · time spent planning is appropriate · info sufficient for stakeholders · process to adapt plans.

5Project work domain

Bid documents
All documents used to solicit information, quotations, or proposals from sellers.
Bidder conference
Meetings with prospective sellers before bids so all have a common understanding (contractor / vendor / pre-bid conference).
Explicit knowledge
Can be codified with words, numbers, pictures.
Tacit knowledge
Personal, hard to articulate: beliefs, experience, insights.

Includes: managing flow of work and changes · keeping the team focused · efficient systems and processes · communicating with stakeholders · managing materials and logistics · working with procurement · monitoring changes · project learning and knowledge transfer.

5Processes, constraints, procurement

  • Review task boards for bottlenecks and impediments.
  • Large and critical projects have more process than small or less significant ones.
  • Optimize: lean production, retrospectives/lessons learned, "where is the next best funding spent?"
  • Spend just enough time on process conformance.
  • Competing constraints: fixed dates, regulations, budget, quality policies; a new requirement may expand schedule/budget; a budget cut may relax quality or reduce scope.
  • Most PMs do not have contracting authority; they work with contracting officers to write the RFP, SOW, terms and conditions.
Bid document Used to
RFI Learn what technologies/vendors exist
RFP Invite vendors to bid on building a defined solution
RFQ Ask for best price and timeline for a known item (500 laptops)

Check: efficient performance · tailored processes · appropriate communication · efficient physical resources · effective procurement · handled change · improved capability.

6Delivery domain

Definition of Done (DoD)
Checklist of all criteria for a deliverable to be ready for customer use.
Quality
The degree to which inherent characteristics fulfill requirements.
Cost of Quality (COQ)
All costs over the product life for prevention, appraisal, and failure to meet requirements.
  • Releasing throughout the life cycle delivers value during the project; value continues after it ends.
  • The business case gives the justification and projected value.
  • Scope = what to deliver; quality = the performance levels required.
  • Quality costs are often borne by the sponsoring organization (overhead, training, audits).
  • Suboptimal outcomes exist in every project (experimental work, missed market window).

Check: contributes to strategy · realizes outcomes · benefits on time · clear understanding of requirements · stakeholders accept deliverables.

7Measurement domain

Metric
Description of an attribute and how to measure it (work progress %).
Baseline
Approved version of a measure used for comparison to actuals.
Dashboard
Charts and graphs showing progress against important measures.

Why measure: evaluate vs plan · track resources/work/budget · accountability · inform stakeholders · benefits on track · focus trade-off conversations · meet acceptance criteria.

The value is in the conversations about using the data, not in collecting it.

7Effective measures

KPI Nature Examples
Leading Proactive, predict changes or trends Rate of scope change requests; team workload balance
Lagging Reactive, backward-looking, after the fact Cost variance; deliverables completed; customer satisfaction scores
TrapSMART here = Specific, Meaningful, Achievable, Relevant, Timely. M is Meaningful, not Measurable.

7What to measure (7 categories)

Category Examples
Deliverable metrics Errors/defects, performance, technical performance
Delivery WIP, lead time (need → delivery), cycle time, process efficiency
Baseline performance Start/finish dates, effort, duration, schedule variance
Resources Planned vs actual utilization and cost
Business value Cost-benefit ratio, ROI, NPV
Stakeholders NPS, mood chart, morale, turnover
Forecasts ETC, EAC, VAC

Presenting info: dashboards · information radiators · visual controls (task boards, burn charts).

Check: reliable status · actionable data · timely actions · achieving targets from reliable forecasts.

8Uncertainty domain: definitions

Uncertainty
Lack of understanding and awareness of issues, events, paths, or solutions.
Ambiguity
Being unclear, difficulty identifying causes, or multiple options to choose from.
Complexity
Hard to manage due to human behavior, system behavior, ambiguity.
Volatility
Possibility of rapid and unpredictable change.
Risk
Uncertain event or condition that, if it occurs, has a positive or negative effect on objectives.

Environment sources: economic · technical · legal · physical · ambiguity · social/market · political.

8Ambiguity, complexity, volatility

  • Conceptual ambiguity: people use similar terms differently ("the schedule was reported on track last week").
  • Situational ambiguity: more than one outcome is possible (multiple options).
Complexity type Techniques
Systems-based Decoupling (disconnect parts) · Simulation (analogous scenarios: airport ↔ malls)
Reframing Diversity (many perspectives, Delphi) · Balance (mix data types)
Process-based Iterate · Engage stakeholders · Fail safe (redundancy, graceful degradation)

Volatility usually hits cost and schedule; handle with alternatives analysis and cost/schedule reserve.

8Risk

  • Negative risks = threats; positive = opportunities. All projects have risk.
  • Overall risk is a function of complexity, ambiguity, volatility; if too high the project may be cancelled.
Threat Opportunity
Avoid Exploit
Transfer Share
Mitigate Enhance
Escalate Escalate
Accept Accept
  • Contingency reserve → identified risks. Management reserve → unknown, unplanned in-scope work.
  • Risk review: daily standups surface blockers (threats) and breakthroughs (opportunities); frequent demos too.
  • Opportunity example: a time-and-materials subcontractor finishing early.
CH 1.3

Tailoring, Models, Methods, and Artifacts

Why, what and how to tailor · model families · methods · artifacts

DEFTailoring

The deliberate adaptation of the PM approach, governance, and processes to make them more suitable for the given environment and the work at hand.

Considers the development approach, processes, life cycle, deliverables, and people to engage. Variables include criticality and number of stakeholders: a nuclear reactor needs far more rigor than an office building.

7Competing demands to balance

  1. Delivering as quickly as possible
  2. Minimizing project costs
  3. Optimizing value delivered
  4. High-quality deliverables and outcomes
  5. Compliance with regulatory standards
  6. Satisfying diverse stakeholder expectations
  7. Adapting to change

3Why tailor? (benefits)

  1. More commitment from team members who helped tailor
  2. Customer-oriented focus
  3. More efficient use of resources

5What to tailor

  • Life cycle and development approach: e.g. a data center: predictive for the building, iterative for computing = hybrid at project level.
  • Processes: elements Added, Modified, Removed, Blended, Aligned.
  • Engagement: People, Empowerment, Integration.
  • Tools: team knows best, but cost and leaders' constraints apply.
  • Methods and artifacts: suit the environment and culture; documents and templates fit the project.
HookProcesses: "A Man Rarely Buys Apples". Engagement: PEI.

4The tailoring process

1 Select initial development approach→2 Tailor for the organization→3 Tailor for the project→4 Implement ongoing improvement
  • Step 1: choose the approach best suited (agile, waterfall...).
  • Step 2: modify based on organizational modifications (methodology for small vs large/sensitive projects).
  • Step 3: adjust for size, criticality and other factors.
  • Step 4: inspect and adapt (review points, phase gates, retrospectives). Tailoring is not a one-time exercise.
Hook"Some Organizations Prefer Improvement": Select · Organization · Project · Improvement.

3Tailoring for the project

Product/deliverable (7): compliance/criticality · type of product · industry market · technology · time frame · stability of requirements · security.

Project team (5): team size · team geography · organizational distribution · team experience · access to customer.

Culture (4): buy-in · trust · empowerment · organizational culture. Culture = shared norms, beliefs, practices (formal and hierarchical, agile, risk-averse, innovation-driven).

SITUATIONTailoring suggestions (slide 21)

Situation Tailoring suggestion
Poor quality deliverables Add feedback verification loops and quality assurance steps
Team unsure how to proceed Add guidance, training, and verification steps
Long delays waiting for approvals Streamline approvals: fewer people authorized up to value thresholds
Too much WIP or high scrap Value stream mapping and kanban boards to visualize work
Stakeholders disengaged or negative Check information sharing; deeper engagement over simple communication
Lack of visibility of progress Ensure measures are collected, analyzed, shared, discussed
Issues/risks keep surprising the team Explore root causes and gaps in processes

MMAModel · Method · Artifact

Model
A thinking strategy to explain a process, framework, or phenomenon.
Method
The means for achieving an outcome, output, result, or deliverable.
Artifact
A template, document, output, or project deliverable.

Lists are not exhaustive or prescriptive. Using them costs time and expertise. Avoid anything that: duplicates or adds unnecessary effort · is not useful · produces incorrect or misleading info · caters to individual needs over the team's.

MODELSCommonly used models

Family Models
Situational leadership Situational Leadership® II (style by team development level) · OSCAR (conversations, problems, development)
Communication Cross-cultural communication · effectiveness of channels (clarity, speed, richness, recordability, accessibility, suitability) · gulf of execution and evaluation (UX)
Motivational Hygiene vs motivational factors · intrinsic vs extrinsic · hierarchy of needs · Theory X, Y, Z
Change ADKAR® (individual transformation) · 8-step process for leading change · Virginia Satir (emotional response) · Transition model
Complexity Cynefin (avoid rigid processes on unpredictable work) · Stacey matrix (waterfall vs agile vs hybrid)
Team development Tuckman ladder · Drexler/Sibbet (7 stages)
Other Conflict · negotiation · planning · process groups · Salience (prioritize stakeholders)
Slide note"Don't memorize, understand": know what each model is for.

DETAILModel details worth knowing

  • Hygiene: salary, benefits, conditions, policies, job security. Motivators: achievement, recognition, advancement, responsibility, the work itself, growth.
  • Maslow: physiological → safety → love/belonging → esteem → self-actualization.
  • 8-step change: urgency → guiding coalition → strategic vision → volunteer army → remove barriers → short-term wins → sustain acceleration → institute change.
  • Drexler/Sibbet: orientation → trust building → goal clarification → commitment → implementation → high performance → renewal.

METHODSMethods and artifacts

Method categories: data gathering and analysis · estimating · meetings and events · other.

Artifact categories: strategy (strategic plan, vision/mission, roadmap, business case) · logs and registers (issue log, risk register) · plans · hierarchy charts (WBS, OBS) · baselines (budget, schedule) · visual data · reports · agreements and contracts · other.

Slides 26 and 34–41 map every model, method and artifact to the performance domains they support, all within the system for value delivery and the internal/external environment.

CH 2

The PM and SE Process Context: Strategy, Structure, and Culture

Pinto ch. 2, without the cancelled slides

DEFStrategic management

The science of formulating, implementing, and evaluating cross-functional decisions that enable an organization to achieve its objectives.

  1. Developing vision and mission statements: what the organization hopes to become.
  2. Formulating, implementing, and evaluating: projects are the key ingredients of strategy implementation (SWOT, long-range objectives, alternatives).
  3. Making cross-functional decisions
  4. Achieving objectives

2.1Projects reflect strategy

Strategy Project
Technical/operating initiatives New plants, modernized facilities
Greater market penetration New product development
Streamlined business processes Reengineering
Change of direction / portfolio New product lines
New strategic alliances Negotiation with supply chain
Match or beat competitors Reverse engineering
Supply chain communication Enterprise IT efforts
Cross-functional interaction, faster introduction Concurrent engineering

CASEAirbus A380 and the TOWS matrix

Airbus and Boeing saw the same facts (air traffic doubling every 15 years) but chose different strategies. Airbus: much bigger planes for congested airports. Boeing: medium-sized wide-body jets for more frequent travel between growing cities. The A380 failed because of the strategic decision.

TOWS Strategy Projects that...
SO Maxi-Maxi use strengths to maximize opportunities
ST Maxi-Mini use strengths to minimize threats
WO Mini-Maxi minimize weaknesses by taking advantage of opportunities
WT Mini-Mini minimize weaknesses and avoid threats

STAKEStakeholder management

Project stakeholders: all individuals or groups who have an active stake in the project and can potentially impact, positively or negatively, its development. Stakeholder analysis exposes seemingly irresolvable conflicts.

Internal External
Top management Clients
Accountant Competitors
Other functional managers Suppliers
Project team members Environmental, political, consumer, other intervenor groups

Intervenor groups can effectively intervene and disrupt the project (environmental groups delaying Dakota Access and Keystone XL pipelines).

2.3Stakeholder relationships

  • Top management: control PMs and regulate their freedom of action.
  • Accountant: supports and actively monitors project budgets.
  • Other functional managers: staff are "on loan" from their departments.
  • Clients: want the project quickly so the investment starts generating returns.
  • External environment: competitors, suppliers, etc.
  • Also: parent organization, project team.

3Organizational structure: 3 elements

  1. Formal reporting relationships: who reports to whom, levels in the hierarchy, span of control.
  2. Groupings: individuals into departments, departments into the organization.
  3. Systems design for effective communication, coordination, integration across departments.

Forms: Functional (people performing similar activities grouped into departments) · Project (people grouped into temporary project teams) · Matrix (dual hierarchy: functions and projects have equal prominence).

2.2–2.4Strengths and weaknesses for project management

Structure Strengths Weaknesses
Functional No disruption to the firm's design · in-depth knowledge and intellectual capital · standard career paths Functional siloing · lack of customer focus · longer time to complete projects (slow communication) · varying interest or commitment
Project PM has sole authority · improved communication · effective decision making · creates PM experts · rapid response to market opportunities Expensive to set up and maintain teams · loyalty to the project over the firm · hard to keep a pooled supply of intellectual capital · worry about the future after the project
Matrix Suited to dynamic environments · equal emphasis on PM and functional efficiency · coordination across units · maximizes scarce resources Two bosses · negotiation to share resources · workers caught between project and functional demands

Pure project organizations: construction firms, Boeing/Airbus, pharma, software consulting, R&D. Each project is a self-contained business unit with a dedicated team. In a matrix, a VP of projects controls PMs who borrow staff from functional groups.

HEAVYHeavyweight project organizations

Fully dedicated project organization, e.g. Lockheed's "Skunk Works": small autonomous team of hand-picked experts, PM given full authority, status and responsibility.

  • Project manager authority expanded
  • Functional alignment abandoned for market opportunism; direct reporting to top executives
  • Focus on the external customer

Fig 2.8 (survey): effectiveness rises from functional toward project-based structures; project organization rated best for new product development, project matrix best for construction.

PMOProject management offices

Centralized units that oversee or improve PM. Resource centers for: technical details, expertise, repository, center for excellence. Shifts PM burden (scheduling, resource allocation, monitoring) to support staff.

Level Where
Level 3 Corporate: overall support function
Level 2 Functional: within one business unit
Level 1 Project: direct support for each project

PMOPMO forms and models

Form Control Role
Supportive Low Consultative; provides resources and training
Controlling Moderate Requires compliance with adopted standards
Directive High Directly manages projects
Model Purpose
Weather station Only monitors and tracks status, no influence
Control tower Protects PM as a skill; improves methodology and helps PMs apply it
Resource pool Supplies skilled PMs and professionals to projects

CULTUREOrganizational culture

The third contextual variable. The unwritten rules of behavior, or norms, shared by some subset of members and taught to all new members.

  • Unwritten: often not written down
  • Rules of behavior: how best to react to events
  • Held by some subset: may or may not be companywide
  • Taught to new members: learned by observing others

7 factors: technology · environment · geographical location · reward systems · rules and procedures · key organizational members · critical incidents (when the real culture becomes visible).

GE jet engines: competitive, high-pressure, rewards aggressiveness, high burnout. Rolls-Royce: paternalistic, rewards loyalty and long tenure.

4How culture affects project management

  1. Departmental interaction: cooperative cultures beat disinterested or adversarial ones.
  2. Employee commitment to goals: commitment and self-sacrifice beat "going through the motions".
  3. Project planning: people pad estimates when the culture punishes lateness; a culture of trust gives honest estimates.
  4. Performance evaluation: if caution is rewarded, PM approaches become cautious too.
Hook"Departments Expect Planned Performance": Departmental, Employee, Planning, Performance.
CH 3

Team

Team development · trust · conflict · accountability · team models · managing people

QUOTEWhy projects fail (McConnell)

Software projects fail because the team lacks the knowledge to conduct the project, or lacks the resolve (determination, commitment, mental toughness) to conduct it effectively.

Skill Example activity
Planning Which resources are pre-assigned?
Negotiation Getting the best resources; sharing
Hiring Outsourcing, virtual teams
Risk management What if resources become unavailable?
Judgment Are assumptions made about skill levels?

5Types of influence (power)

Type Based on
Formal (legitimate) Authority granted by hierarchy or role
Reward Ability to offer incentives
Penalty (coercive) Threat or use of punishment
Expert Specialized knowledge or skills
Referent Personal traits, charisma, likability

Leadership styles: directing, facilitating, coaching, supporting, autocratic, consultative, consensus, delegating, bureaucratic, charismatic, democratic/participative, laissez-faire, analytical, driver, influencing.

Hook"Legit Rewards Can Earn Respect": Legitimate, Reward, Coercive, Expert, Referent.

NEEDSNeeds and the team

Self-actualization
Esteem
Social
Safety
Physiological
Individual (Maslow)
Results
Accountability
Commitment
Managed conflict
Trust
Team (built from the bottom)

Lower-level needs must be satisfied before higher ones. The rest of the chapter follows the team pyramid: trust → conflict → commitment → accountability → results.

5Tuckman's model

  1. Forming: group comes together, gets to know each other.
  2. Storming: chaotic competing for leadership and influence, trials of group processes.
  3. Norming: agreement on how the group operates.
  4. Performing: practices its craft, effective in meeting objectives.
  5. Dissolving / Adjourning

3Team structure by objective

Objective Traits Structure
Problem resolution Complex, poorly defined; 1–3 issues (a showstopper defect); urgency and pressure Flexible roles, rapid decisions, temporary task force
Creativity New product development; divergent thinking, experimentation, tolerates ambiguity Looser hierarchy, diverse skills, risk-taking culture
Tactical execution Carry out a well-defined plan; clear roles; timelines and accountability Hierarchical or matrix, tight controls, performance tracking

TRUSTBuilding trust

  • Trust is the foundation of teamwork.
  • Trust is about vulnerability: admitting mistakes, asking for help, saying "I don't know".
  • Takes time (consistent behavior, follow-through, shared experiences) and must be maintained.
  • Technique: behavioral profiling (Myers-Briggs) to admit strengths and weaknesses.

Establishing a basis of trust: earned, not granted · keep open communication · be fallible · lead by example, not mandate · complete commitments on time (explanation, not excuse) · don't confuse friendship with leadership.

CONFLICTManaging conflict

  • Healthy conflict requires trust: unfiltered, passionate debate around issues.
  • Conflict norms = rules of engagement (tone, language, timing).
  • Avoiding conflict leads to groupthink (harmony over critical thinking), suppressed dissent, poor decisions.
Technique Meaning
Confronting (problem solving) Resolve the root cause through open, honest dialogue
Compromising Middle ground by mutual concessions
Withdrawal (avoidance) Delay or sidestep
Smoothing (accommodating) Preserve harmony by downplaying differences
Collaborating Integrate perspectives for a creative solution
Forcing Impose a solution by authority or pressure

6Problem solving and resolving conflict

Define root problem→Analyze→Identify solutions→Pick one→Implement→Review
  • Successful teams resolve conflict; unsuccessful teams force it to the background.
  • Disagreement ≠ conflict: conflict is a hardening of position and intractability.
  • Conflicts trace to a clash between two parties; outsiders stay neutral; one acts as conciliator.
  • Goal: reduce conflict to a disagreement, then reach consensus; strive for reconciliation.

COMMITCommitment, accountability, results

  • Commitment = clarity (everyone knows what was decided and why) + buy-in (support even without full agreement).
  • Buy-in does not require consensus.
  • Accountability on strong teams occurs directly among peers; the leader models confronting it; best moments are meetings and reviews ("we committed to five stories but completed three").
  • Results: put team results over individual or department needs; make results public and visible.

RACIResponsibility assignment

RACI: Responsible (does it) · Accountable (owns it) · (Support, in RASCI) · Consulted · Informed.

  • RAM: resource planning tool, who does what; planning and tracking; identifies authority, accountability, responsibility; "who" can be a person, team or department; can total rows/columns.
  • Skills matrix: resources on one axis, skills on the other; cells are X's or numbers (level, years).

MODELSTeam models

Model How it works Notes
Early philosophies Decentralized/democratic vs centralized/autocratic; variation: controlled decentralized
Business team Technical lead + team at equal status; hierarchical with one principal contact; strong or loose hierarchy Most common, adaptable; default starting point
Democratic team All decisions by the whole team by consensus; leader is the external interface but does not allocate work Works when all members are experienced; a.k.a. self-organizing
Agile groups Variant of democratic; some management decisions delegated; in XP programmers work in pairs with collective code ownership
Chief programmer ("surgical") IBM, 1970s: a superstar writes the core code, supported by backup programmer (co-pilot), program clerk (docs, versions), administrator, toolsmith, language lawyer Problems: talent is rare, resentment, high risk if chief and deputy are unavailable, org grades may not fit
Skunk works Talented creative developers placed away from the mother ship Pro: ownership and buy-in. Con: little visibility. For exploratory work, not narrow problems
SWAT team Highly skilled team whose skills tightly match the goal; often work together Security SWAT, Oracle performance team
Large teams Communication grows with the square of people: 50 programmers ≈ 1,200 paths; formalize, use hierarchy Units under 10 (7 ± 1); optimal 4–6 developers + tech lead

PEOPLEManaging people: activities and motivation

People are the most important assets. Management activities (related to people): problem solving · motivating · planning · estimating (how fast people work) · controlling · organizing.

Motivation is needs-based: basic (food, sleep) · personal (respect, self-esteem) · social (acceptance). Physiological and safety needs are assumed met; social, esteem, self-realization matter most to managers. Unmet lower needs pull focus back down.

Need How to satisfy
Social Communal facilities; allow informal communication
Esteem Recognition of achievements; appropriate rewards
Self-realization Training; responsibility

3Personality types and group composition

Type Motivated by All-same group
Task-oriented The work itself Everyone does their own thing
Self-oriented Personal goals (get rich, travel) Everyone wants to be the boss
Interaction-oriented Presence and actions of co-workers Too much chatting

An effective group balances all types (hard: most engineers are task-oriented). Time: 50% interacting, 30% working alone, 20% non-productive.

Leadership depends on respect, not titular status; can have technical and administrative leaders; democratic beats autocratic; support technical career paths.

GROUPCohesiveness, loyalty, communication

  • Cohesive group: the group matters more than any individual. Advantages: group quality standards · work closely (less ignorance) · learn from each other · egoless programming.
  • Encourage via social events, group identity and territory, team-building, openness with information.
  • Groupthink: preserving the group regardless of technical or organizational considerations; prevent it by forcing external involvement.
  • Communication factors: status (higher status dominates) · personalities (too many alike is a problem) · channels (a central coordinator tends to be ineffective).
  • Group size < 10, optimal under 7; break big projects into smaller ones.

HIREChoosing people and staff selection factors

Based on CV, interview, interviews with co-workers, recommendations; psychological/aptitude tests are of disputed usefulness.

  • Application domain experience: must understand the domain
  • Platform experience: matters for low-level programming
  • Programming language: only for short projects
  • Educational background: fades with experience
  • Communication ability: very important
  • Adaptability: shows ability to learn
  • Attitude: important, hard to assess
  • Personality: compatible; no type is best

ENVWorking environment

  • Physical workplace affects productivity and satisfaction: comfort, privacy, facilities; health and safety (lighting, heating, furniture).
  • Environmental factors: privacy (uninterrupted work) · outside awareness (natural light) · personalization.
  • Individual offices increase productivity, but teams also need meeting spaces.
  • "Human resources" treats people as inanimate and interchangeable; treat them as collaborators, stakeholders, teammates.

5The PM's people skills

  1. Interpersonal skills: effective communication (defined protocol, timely, just the right info) · influencing the organization · leadership · motivation (financial incentives are among the least effective) · negotiation and conflict management · problem solving.
  2. Shaping project culture
  3. Managing people
  4. Making people better
  5. Leadership

CULTUREShaping project culture

  • Understand the organization's culture and each member's background (education, experience, generation, personality).
  • Cultural roles: leader · listener/talker · complainer/naysayer · expert · charger/plodder. Stay non-judgmental.
  • Project roles: project manager (plans, tracks) · team leader (builds the team) · development leader (superior product).
  • Project environment: cultural/social factors and international/political factors (time zones, holidays, laws).
  • Monitor role satisfaction (especially at launch), task-to-people fit, and the team's cultural climate.

GUIDEManaging people (Peopleware)

The main problems are sociological, not technological.

  • Gain visibility without micromanagement
  • Review process and products, not people
  • Coordinate, don't manipulate
  • Use your knowledge, not your position of power
  • Channel people, don't put dams in front of them
  • Focus on project and people needs, not your authority

Production-line errors with thought workers: squeeze out error · hard line on "goofing off" · interchangeable workers · optimize the steady state · run by the book · eliminate experimentation.

GROWMaking people better

  • Make professional development a project goal; short-term (this project) and long-term (future) goals.
  • Members set personal improvement goals (technical, leadership, domain, communication, management).
  • Track individual time in detail for a fixed interval: awareness-building, not monitoring.
  • PSP (Personal Software Process): manage quality, make commitments you can meet, improve estimating, reduce defects.

LEADTechnical vs adaptive leadership

Leadership = the capacity to mobilize a group to solve the most challenging problems (not authority).

Technical Adaptive
Problems Solved by known means Not solvable by known means
Driver Vision (leader's personal view) Sense of purpose ("why does this matter?")
Tool Personality (charisma, expertise) Progress (learning, iteration)

Adaptive leaders lead with good questions, need clarity of purpose, and can delegate known problems.

CONSENSUSWorking toward consensus

Consensus = everyone feels heard and commits, not that everyone agrees. Simple majority rule can hurt a small team.

  1. Pose the problem or decision
  2. Solicit input on options
  3. Discuss pros and cons
  4. Work toward options with most benefit
  5. Help opponents buy in: persuade, don't dictate

Consensus takes longer than mandate but pays off. Passive/aggressive agreement = subsumed conflict.

Leading people adds: be confident · use all the team's talents.

Memorize

Every list worth points, with its count and a hook. Turn on "Cover lists" to test yourself, then tap a card to reveal.

Don't mix these up

Pairs the exam likes to swap.

Pair First Second
Program vs portfolio Program: related projects for benefits not available individually Portfolio: projects, programs, operations grouped for strategic objectives
Outcome vs output Outcome: end result, benefits and value Output/artifact: the thing produced
Principles vs code of ethics 12 principles: guide behavior, not necessarily moral Code of ethics: 4 moral values (RRFH)
Adaptability vs resiliency Respond to changing conditions Absorb impacts and recover from setbacks
Management vs leadership Means of meeting objectives (process, planning) People (influencing, motivating)
Accuracy vs precision Correctness: close to reality Exactness: level of detail
Contingency vs management reserve Identified (known) risks, PM controls Unknown in-scope work, upper management controls
Product vs project scope Features and functions Work performed to deliver them
Mandatory vs discretionary Required by contract or nature of work; usually can't change Best practice or preference; may change
External vs internal dependency Project and non-project activities; usually can't change Between project activities; may change
Explicit vs tacit Codified in words, numbers, pictures Personal beliefs, experience, insights
Leading vs lagging Predict trends (scope change rate, workload balance) After the fact (cost variance, satisfaction)
Conceptual vs situational ambiguity Same words, different meanings More than one possible outcome
Lead time vs cycle time Need identified → result delivered Time to process the work once started
Model vs method vs artifact Thinking strategy · means of achieving Template, document, output, deliverable
Functional vs matrix Similar activities in departments; silos Dual hierarchy; two bosses
Supportive vs directive PMO Low control, consultative High control, manages projects directly
Weather station vs control tower Monitors and tracks only Protects and improves PM practice
Disagreement vs conflict Difference of opinion Hardened positions, intractable
Clarity vs buy-in Everyone knows what was decided Support even without full agreement
Responsible vs accountable Does the work Owns the outcome, answerable
Skunk works vs SWAT Creative team away from the org; low visibility Skills tightly match a specific goal
Technical vs adaptive leadership Known means; vision; personality Unknown means; sense of purpose; progress
Skunk Works (Ch 2) vs skunk works (Ch 3) Lockheed's heavyweight project organization A team model with high ownership

Practice exam

MCQ and true/false grade instantly. Matching grades per pair. Listing and short answers are graded by keywords: typos and plurals are tolerated, order doesn't matter.

0 / 0
Answer and check questions to build your score.
Chapter
Type