Multiple Choice Questions
Q1
(2 points)
The Project Management Spectrum focuses on the four P's. Which
of the following is NOT one of them?
Q2
(2 points)
Which of the following is NOT a key stakeholder type in software
projects?
Q3
(2 points)
A team leader needs to develop three key skills. Which of the
following is one of them?
Q4
(2 points)
What does high "Fan-out" for a function indicate?
Q5
(2 points)
In risk management, which strategy aims to reduce the
probability that a risk will arise?
Q6
(2 points)
According to the triple constraints for software projects, which
three factors must be balanced?
Q7
(2 points)
In the Critical Path Method (CPM), what is "Total Slack"?
Q8
(2 points)
Which risk type relates to "staff turnover"?
True/False Questions
Q9
(1 point)
The Critical Path is the shortest path through a project network
diagram.
Q10
(1 point)
Risk monitoring should be done only at the beginning of the
project.
Q11
(1 point)
In agile teams, self-organizing teams make their own decisions
about project management and technical matters.
Q12
(1 point)
The Early Finish (EF) of a task is calculated as: EF = ES +
Duration