📊 Chapter 4: Project Management Quiz

Test your knowledge on Software Project Management

Multiple Choice Questions

Q1 (2 points) The Project Management Spectrum focuses on the four P's. Which of the following is NOT one of them?
Q2 (2 points) Which of the following is NOT a key stakeholder type in software projects?
Q3 (2 points) A team leader needs to develop three key skills. Which of the following is one of them?
Q4 (2 points) What does high "Fan-out" for a function indicate?
Q5 (2 points) In risk management, which strategy aims to reduce the probability that a risk will arise?
Q6 (2 points) According to the triple constraints for software projects, which three factors must be balanced?
Q7 (2 points) In the Critical Path Method (CPM), what is "Total Slack"?
Q8 (2 points) Which risk type relates to "staff turnover"?

True/False Questions

Q9 (1 point) The Critical Path is the shortest path through a project network diagram.
Q10 (1 point) Risk monitoring should be done only at the beginning of the project.
Q11 (1 point) In agile teams, self-organizing teams make their own decisions about project management and technical matters.
Q12 (1 point) The Early Finish (EF) of a task is calculated as: EF = ES + Duration